HomeMy WebLinkAbout03/15/2005 Staff ReportsSTAFF REPORTS TO COUNCIL
Building Department
Clerk's Office
Court
Finance Department
Parks and Recreation
Department
Planning Department
Police Department
Public Works /
Engineering Department
Human Resources Department
Water Department
h/admin/forms/staff reports
For: February 2005
~ -~
~VIAR~1\lA
/tom
TOWN 01= MARANA
TEAM WORK-
Is all staff working together in outstanding ways, with extraordinary cooperative effort
to accomplish ordinary tasks
TO: Mayor Bobby Sutton, Jr.
Town Council
Mike Reuwsaat, Town Manager
FROM: Water Department Staff
SUBJECT: February 2005 Department Report Update
DATE: March 2005
CUSTOMER INFORMATION
3007 Number of Customers Billed
66 Number of Disconnects
93 Number of New Connects
133 Number of New Services with Meter Installation
22,943,659 Total Gallons sold
44.64 Acre feet pumped (non-trust wells) Picture Rocks, Happy Acres, Palo
Verde, Airport, Sky Diving Center, Continental Reserve and Hartman
Vistas
34.28 Acre-feet wholesale water purchased (trust wells) Marana, La Puerta,
Oshrin, Falstaff, Honea, and Cortaro Ranch
(325,851 gallons =acre foot)
___. DAILY OPERATIONS
1. 350 Blue Stakes completed.
2. 185 Work Orders completed.
3. Repaired fire Hydrant on Cerius Stravenue
4. Installed Ballards around three fire hydrants along Cerius Stravenue
5. Found a buried valve along Picture Rocks Road. Installed new valve sleeve and
box.
6. Repaired radio read meters.
7. Potholed water lines within the Redemtorist Renewal Center off of Picture Rocks
Road.
8. Began pavement cuts for new service lines at the airport.
9. Construction inspections for Ironwood Reserve offsite water and Heritage Park
Road.
10. Collected GPS data of system infrastructure.
WATER SERVICE AGREEMENTS BEING NEGOTIATED
1. Cascade Development-Addendum to Hartman Vistas
2. Oasis Development-Addendum to Hartman Vistas
3. Santoria Estates (on West side of Old Silverbell North of Linda Vista
intersection).
4. Willow Ridge Agreement is pending.
~n. 5. Agreements for Water Service in San Lucas to Blocks 1-12 Complete.
6. Addendum to Vanderbilt Farms is pending.
OTHER
1. Discussions of regional reliability and terminal storage of C.A.P. water being
discussed.
2. Anon-potable Master Plan is underway. Discussions with Arizona Department of
Water Resources.
3. Non-potable system and storage are in the discussion, and draft, design stage,
for the east side of I-10, from Tangerine Rd. to the Pinal County line.
4. Sunset Ranch Estates rate comparison in Progress.
5. Regional water supply organization discussions on hold.
6. Water Issues Being Elevated with Tucson Water.
7. Effluent and Marana Wastewater Treatment Plant in discussions with Pima
County.
8. Flowing Wells excess C.A.P. allocation transfer in process at Arizona Department
of Water Resources.
9. As of January The Water Department started billing for sewer on our water bills.
2
~~. VOLUME 3, ISSUE 1 .SOWN pF MARCH 2005
,,
1 7
9 7
gRIZONA
CAPITAL IMPROVEMENT PROGRAM-CIP PROJECTS IN DESIGN
MISSION STATEMENT:. MARANA CONTINENTAL RANCH
LIBRARY:
"The Town of Marana This Project consists of selecting an
Department of tPubiic Architectural Firm for design; design
lvorks is committed o ` and construction of a new library to be
.providing quality service
by consistently deliver- located in the Town near the
ing anrf maintaining reli- Walgreen's store located at the
able, safe public facilities- corner of Cortaro Road and Silverbell
with a productive, re= Road. The new library will be located
spectful, and ethical south and somewhat east of the
workforce" Walgreens. The library will contain
approximately 15,000 square feet of
'VALUE STATEMENTc floor space along with an additional
5,000 square feet of shell area that
Our operating values are•" will be bid as an additive alternate.
This space is intended to be for the
use of the Town. The library is
• SATISFACTION intended to house an eventual
• RESPECT 100,000 volume book collection with
state of the art technology, computer
• COMMUNICATION lab, large meeting room, and small
REUAB1uTY study rooms. The delivery method for
the Project, as selected by Pima
• PRODUCTIVITY ', County, is Design-Bid-Build scenario.
• CiUAUTY Estimated Design Time: Pima
ETHICAL County anticipates a ten (10) month
design phase from issuance of the
• CONSISTENCY Notice to Proceed.
SERVICE
Estimated Construction
Time: Pima County
anticipates a twelve (12)
month construction phase
from issuance of the Award of
the Bid.
Status: The architectural
Services contract with Richard
& Bauer has been executed
by both the County and the
Architect. The Notice to
Proceed is anticipated to be
issued within two (2) weeks.
The kick-off meeting is
tentatively scheduled for the
week of 06 March, 2005
HONER HEIGHTS ROADWAY IMPROVEMENTS:
This Project will involve the development of construction plans for roadway and
drainage improvements for Honea Heights subdivision, located between
Sanders and Sandario Road, between Moore Road and the Santa Cruz River.
Estimated Construction Time: Following completion of the Honea Heights
.Sewer, approximately 1st quarter of 2006.
Status: Fees and scope of work are being negotiated.
•.~.•.e..~R,..
Inside this issue:
CIP Projects in i-4
Design
CIP Projects in 5-6
Construction
Completed Projects 7-8
Traffic Division 9
Environmental 10-12
Division
~t~Ejj'A~iTNIENT;OF,P1~B~.;'C ~~. .
~M~ ~~ r
~~
'`''f
CiP PRfl]ECTS 'IN DESIGN (cantin~ed),
TWIN PEAKS INTERCHANGE:
This Project consists of Environmental Assessment clearance, DCR, and 15% plans for the corridor alignment, Phase
I; final design for TI, grade separated railroad structure east of I-10, and connecting the existing roadway system to the
east, Phase II.
Estimated Construction Time: 4th quarter of 2006.
Status: Staff has completed the review of the Traffic Impact Analysis for the Project, and the comments have been
transmitted to the Consultant for inclusion in the final report.
Consultant is revising the EA to reflect the mitigation measures which were agreed to by the Town and ADOT during
our meeting in January, 2005.
Staff met with personnel from FHWA and ADOT in February to discuss the logistics of receiving the federal funding
allocated to the Project.
The Consultant and the Town are continuing to work on the public hearing which is an ADOT requirement.
The EA and DCR are anticipated to be completed in the first quarter of 2005.
MOORE ROAD IMPROVE-
MENTS:
This Project will involve the
development of a Preliminary
Design Report and subsequent
final Construction Documents.
The Project consists of improve-
ments to driving surface and
drainage crossings from Camino
de Oeste to Thornydale Road.
Estimated Construction Time:
To be detenmined
Status: The Notice to Proceed
was given to the Design
Consultant on October 23, 2003
The Preliminary Design Report
and Plans have been received.
TANGERINE FARMS ROAD
IMPROVEMENT DISTRICT-
TANGERINE ROAD TI TO
MOORE:
This Project consists of a new
four-lane roadway with a
landscaped median, curb and
gutter, multi-purpose lanes,
sidewalks, landscaping and
drainage improvements.
Estimated Construction Time: To
be determined
Status: The survey for the Project
is underway and is expected to be
complete in the 1 st quarter of 2005.
The Notice to Proceed for the
design phase was issued in January
2005.
INA ROAD BRIDGE IMPROVEMENTS-
BRIDGE OVER THE SANTA CRUZ:
This Project consists of constructing a new
bridge over the Santa Cruz River and
demolishing the existing bridge.
Construction will also include rehabilitating
the existing Grade Control Structure, and
reconstructing the soil cement bank
protection on the east and west side of the
Santa Cruz River. The reconstruction of the
bank protection will include provisions for a
pedestrian path.
Estimated Construction Time:
2008-2009
Status: The Bridge Improvement Plans,
Design Concept Report (DCR), Bridge
Selection Report, Bridge Stability Analysis
and the amended Bridge Inspection Report
have been submitted to ADOT's Phoenix
office. The Town is awaiting final approval
of the ACOE Permit.
DISTRICT PARK BANK PROTECTION:
This Project consists of providing soil cement for bank protection along the west bank of the Santa Cruz River from
Ina Road to Cortaro Road. Phase I of the Project will be from Cortaro Road to the Yuma Wash.
Estimated Construction Time: 3rd quarter of 2005
Status: Tetra Tech is the Design Engineer. Tetra Tech is working on revisions to Phase I of this Project. An
individual 404 permit application has been submitted to the Army Corp of Engineers and is anticipated to be issued
to the Town by the first quarter of 2005. Construction will begin after all permits are obtained, design is complete,
and Rights-of-Way are acquired.
~DfiP~~ > ~~ V~I~KS,
E ,.,~ ,- ~ _ _, .
bt3LtiM~ 3; ISSUE l
_ ._. _ .
CIP PR03ECTS gN. DESIGN (continued)
DCR FOR THE INA ROAD CORRIDOR
PROJECT: This Project will involve the
development of a Design Concept Report
to improve Ina Road and the area south
of Ina Road between Thornydale Road,
I-10, and Orange Grove Road.
Estimated Construction Time: To be
determined.
~ Status: This Project is currently on hold.
HONEA HEIGHTS SEWER IMPROVEMENTS:
This Project consists of constructing/installing the
', sanitary sewer mainline and incidentals for the
', residents of the Honea Heights Subdivision.
Estimated Construction Time: 2nd Quarter 2005
Status: The plans have been approved for bid by
USDA Rural Development.
DCR/DESIGN OF BARNETT LINEAR PARK AND FLOOD CONTROL PROJECT:
This Project involves the development of a Design Concept Report for the Barnett Linear Park and Flood Control
Project. The Project consists of utilizing the existing Barnett Roadway alignment for a major outlet channel/linear
park from I-10 to the Santa Cruz River.
Estimated Construction Time: To be determined.
Status: The Cultural investigation and the multi-purpose concepts are complete for the original scope. The final
Draft Environmental Assessment was submitted and was reviewed by Town Staff. Comments were submitted
back to AMEC mid-January. The Town is waiting for a final report from the Consultant. The final hydraulic study is
underway and preliminary findings are being calculated.
DCR FOR CAMINO DE MANANA/DOVE MOUNTAIN EXTENSION:
This Project involves the development of a Design Concept Report for the possible realignment of Camino de Manana from
its intersection with Linda Vista Blvd to an alignment with Dove Mountain Blvd at Tangerine Road.
Estimated construction Time: To be determined.
Status: This Project is currently on hold.
'-1
z { ".C
r ~,
~:. : 1
SILVERBELL ROAD IMPROVEMENTS- CORTARO ROAD
TO INA ROAD:
This Project consists of reconstructing the roadway from two
lanes to four lanes with curb and gutter, multi-purpose lanes
and sidewalks, and providing for a continuous center turn lane,
f sanitary sewer system construction, and intersection
~. improvements at Ina/Silverbell, which includes a new traffic
signal system.
Estimated Construction Time: 3rd quarter of 2005
Status: Environmental, Biological, DCR, Geotechnical
Reports, Pavement Design Summary, Archaeological and
Drainage Reports are complete and have been accepted. The
404 Permit application has been submitted to the Army Corps
of Engineers (ACOE) and is expected to be complete within the
first quarter of 2005. The third year of Pygmy Owl Survey has
been completed. The Town is in receipt of the final Sanitary
Sewer Basin Study and the Study has been accepted by both
the Town and PCWWM. A public open house was held on
January 15, 2004. The Town is working with ADOT to
determine the best schedule to coordinate the I-10 Widening
Project with the Silverbell Project. The 100% plans have been
received.
`.~ * ~ ~ ~ ~. r I v.
~ ,_
~.. .
;~ - -
-.
~` ~' ~~ -
~ ~, ~ ;
~' ,
,~
jj,9~~~7~J1~l+f~' t~f PUBLIC WORKS:
r„
~~~~
~~~~ ~~ ~/
.. ?_. , r...„ ~ 1.M.~ -~
CIP PRO]ECTS IN DESIGN (continued)
SANTA CRUZ RIVER SHARED Construction will need to be Determination (ED) has been
USE PATH, PHASE I AND II: completed such that the ADOT accepted by ADOT. In late April 2003, the
This Project consists of the design funds are properly tracked; Town selected Castro Engineering for the
and construction of a 14' wide paved however, construction can be path design and Structural Grace for
asphalt path from Cortaro Road to completed as a single project. design of the pedestrian bridges. The
Coachline Blvd. via the EI Rio Park Estimated Construction Time: To artistic concepts for the Project have been
Development. Two pedestrian be determined
presented and endorsed by the Mayor and
bridges provide major drainage Council, Marana Parks Committee, the
crossings for the path. Status: The Environmental Public Works Art Project Committee,
Continental Ranch, Sunflower
Phase I consists of building a shared Homeowners Associations, the
use path between Cortaro Road and Construction Committee and the Building
Twin Peaks in the over bank and Committee. The project was advertised
intermediate bank areas of the Santa '~ and bids were received ;however, bids
Cruz River. Phase II consists of a
. were rejected in the best interest of the
continuation of the shared use path
~ Town. Public Works Staff is in the process
in Phase I from Twin Peaks to EI Rio
.; of evaluatin o tions for Project Delive
9 P f rY
Park. Each phase is partially funded and will make a recommendation to Town
under ADOT's Transportation Management during March 2005.
Enhancement Program.
THORNYDALE ROAD IMPROVEMENTS/
ORANGE GROVE TO CDO WASH:
This Project consists of reconstructing and
widening Thornydale Road to six lanes from
Orange Grove to the CDO Wash along with
the reconstruction/widening of the approach
roads, sidewalks, curb, curb and gutter,
traffic signal modifications, drainage
facilities, median islands, street lighting and
art work are also included as part of the
Project.
Estimated Construction Time: 1st quarter
of 2006
Status: The 100% Improvement Plans have
been received, the Phase I Environmental
Site Assessment, Cultural Resources,
Drainage and Geotechnical (for traffic
signal) Reports have been accepted.
The Traffic Engineering and Access
Management Reports have been accepted.
HELP Loan funding has been approved.
ROW acquisition and utility relocations will
occur during 2005.
CORTARO FARMS ROAD-UPRR TO STARGRASS DRIVE:
This Project consists of reconstructing the roadway from two lanes
to four lanes with a landscaped median, curb and gutter,
multi-purpose lanes, sidewalks, landscaping, drainage
improvements, and intersection improvements which includes a
new traffic signal system at Cortaro Farms Road and Hartman
Lane. An interim Project including turn lanes, a traffic signal, and
a new Town of Marana waterline at the intersection of Cortaro
Farms Road and Hartman Lane will be accelerated ahead of the
final Project.
Estimated Construction Time:
Interim Project: 1 st Quarter 2005, 90 day construction
period
Final Project: 2nd Quarter 2005, 240 day construction
period
Status:
Interim Project: Contract has been awarded. Notice to
Proceed will be issued in March 2005.
Final Project: The 100% Phase II plans have been
received and review is underway by Town Staff. The Traffic
Engineering Report has been accepted. Right-of-Way acquisition
is in process.
r~ ~ ,
y y(. ~,;,
._ ___
~,~ ~ i ~
-. - _ i
] ~QEPAR~ ~ f~ i3M~ ~, I$SU E 1-
CIP PR03ECTS IN CONSTRUCTION
TOWN OF MARANA MUNICIPAL COMPLEX:
This Project consists of the design and construction of a
new Town Government Complex and will integrate the
Muniplex and surrounding facilities with the Ora Mae
Harn Park which will eventually abut the Barnett Linear
Greenbelt Park and Flood Control Channel that will run
from I-10 to the Santa Cruz River. This linear park will
also serve as a relief conduit for excess water from the
Tortolita Mountain fan run off.
Status: During February 2005, D.L. Withers, the CM,
turned over Buildings B & C (Marana Police Department
and Marana Courts respectively) to the Town. Both the
Marana Courts and the Police Department have
successfully transitioned into their new
accommodations. The Contractors can now complete
final Testing and Balancing (T&B) for HVAC Mechanical
systems. Completion of minor punch list items is
on-going.
In Building A, third floor, the ceiling the is being
installed, mill work is on-going, and carpet installation
began at the end of the month with furniture installation
to begin in March.
Security, Audio/Video (AN) Controls, data and
telecom, special systems installation is on-going
throughout Building A.
Important milestones of Courts and MPD, 911/
Dispatch, moving into their new buildings were
achieved in February.
~ ~` }q,.
Tony Casella and the IT Department have moved into
their new offices in Building A (Administration and
Council); along with 911/Dispatch Department into
Building B. Much credit goes to Tony, his IT Staff, and his
subcontractors for making the move possible.
In Building A, first floor, the Council Chamber has been
painted and the ceiling grid installed, with HVAC; electric
and controls are 90% complete, handrails have been
installed in the Atrium Lobby, the public elevators are
90% complete, and the ceiling grid in the reception area
is in the process of being installed.
In Building A, second floor, the ceiling is complete, the
flooring is 95% complete, furniture is being installed, hand
railing is being installed on the balcony with pre-finished
metal trim, and flooring and lighting continues.
Continuous rain has produced delays for site flatwork,
as well as causing delays and inconvenience with
general construction. However, concrete sidewalks
are being placed when possible. Rain also delayed
progress of stone work and general off-site work on the
roads and utilities for Grier Road, Civic Center Drive,
and Marana Main Street.
A model of the Project continues to be on display
located in the Town Hall for viewing.
``~ ~ _ -~
~j e, ^
- 1
~ ~ ~ ~I+ PUH1.iC WORKS
s~
~~~v „~. ._. ..
CIP COMPLfTfQ PRO]ECTS
^~"'"
TOWN SEAL: ART FOR MUNICIPAL COMPLEX:
The Town has commissioned local artist To Ree'Nee
Wolf Keiser to produce three Town Seals in Italian glass
mosaic tiles to go into the new Municipal Complex.
To Ree'Nee produced designs and a completed three
foot seal to present to the Building Committee and to the
Mayor and Council for approval. The pictures shown
herewithin are two of the Town Seals in production.
These Seals will be displayed throughout the new Town
I Complex. To Ree'Nee is also producing a four foot
diameter Seal that will go on the wall behind the Council
I Dais in the Council Chamber.
-y
~~~
iVOLUM~ 3;'t~
NORTHWEST MARANA TOWN CENTER, ROADS,
INFRASTRUCTURE. AND OFF-SITE IMPROVEMENTS:
This Project will design and construct the offsite utilities,
roads, landscape, and other infrastructure and establish
the layout of the main Town Center corridors.
Status: Civic Center Drive has been opened up from
Barnett Road to the Marana Apartments and Marana
Main Street. Civic Center Drive opened to the N.W. Fire
Station #36 during February. Street lighting has begun on
these streets and will be complete in March. Landscaping,
sidewalks, and paving installation on Main Street and
', Civic Center Drive is progressing and will continue
'through March. Underground utilities on Grier Road are
expected to be complete in early March, after which
curbs, sidewalks, and paving on Grier Road and Civic
Center Drive at Lon Adams is expected to begin and
continue through early July, 2005.
~DEP~rR~'ME~i"i'r~3~ ~ ~ ~~ Y
~~
CiP COMPLETED PRC},7ECTS
PAVEMENT PRESERVATION
2000 PAVEMENT PRESERVATION COI~~IPLETED JUNE 2000
2001 PAVEMENT PRESERVATION COMPLETED JULY 2001
2002 PAVEMENT PRESERVATION COMPLETED JUNE 2002
2003 PAVEMENT PRESERVATION COMPLETED OCTOBER 2003
2003 WADE RD OVERLAY, W OF SILVERBELL COMPLETED DECEMBER 2002
PARKS
CONTINENTAL RANCH NEIGHBORHOOD
PARK C.R. PARCELS 13 & 14 COMPLETED FEBRUARY 2004
SANTA CRUZ CORRIDOR TRAIL PHASE I COMPLETED APRIL 2004
COYOTE TRAILS ELEMENTARY SCHOOL
PARKING AND SPORTS FIELD IMP. COMPLETED FEBRUARY 2003
EL RIO PARK COMPLETED DECEMBER 2003
TRANSPORTATION
EMIGH ROAD, SANDARIO TO SANDERS
NEW WESTBOUND CORTARO ROAD BRIDGE
OVER THE SANTA CRUZ RIVER
CORTARO ROAD IMPROVEMENTS,
SILVERBELL TO 1-10
SANDRA ROAD BUS TURNAROUND
EMIGH ROAD DRIVEWAY/DRAINAGE,
AT MARANA HIGH SCHOOL
CORTARO ROAD REALIGNI~~NT,
1-10 TO CERIUS STR~IVENUE
LINDA VISTA BLVD., EL CAI~IINO DE MANANA
TO 1 /4 MILE WEST OF HARTMAN
'I SCENIC DRIVE IMI'ROVEI~~NTS
TANGERINE ROAD, BREAKERS TO
THORNYDALE
TANGERINE ROAD PARK AND RIDE
CO1~IPLETED AUGUST 2001
COMPLETED MARCH 2002
COMPLETED FEBRUARY 2003
COMPLETED JUNE 2003
COMPLETED JUNE 2003
COMPLETED JULY 2003
COMPLETED APRIL 2004
C0~IPLETED JUNE 2004
COMPLETED APRIL 2004
COMPLETED SEPTEMBER 2004
$347, 400.00
$511,700.00
$1,035,900.00
$1,082,500.00
$46,700.00
$2,608,600.00
$128,700.00
$895,200.00
$213,300.00
$996,100.00
$3,165,400.00
$7,941,700.00
$17,400.00
$17,000.00
$876,700,00
$82,900.00
$279,500.00
$1,589,600.00
$305,600.00
. •. ~'woR"arY ~ '9f~
~B~ic woRKS vo~uM~ 3, iss~~ ~
CIP COMRLE7ED PRO]ECTS (co.ntinued)
c ~;~~i!~~ifa.,t"`r' G= CGI~f ~L.FTEE~ P~,t~JEG i S ~ccsr~tsruec'
TRAFFIC SIGNALS/LIGHTING
TRAFFIC SIGNALS, INA/
SILVERBELL INTERSECTION COMPLETED FEBRUARY 2002 $124,000.00
COSTCO DRIVE STREET LIGHTING COMPLETED MAY 2003' $41,200.00
SAFETY IMPROVEMENTS
HANDICAP RAMPS AT VARIOUS LOCATIONS COMPLETED FEBRUARY 2002 $97,700.00
COACHLINE BLVD. SIDEWALKS
LANDSCAPING, N/0 TWIN PEAKS COMPLETED OCTOBER 2003 $289,200.00
XQEPAR7MEN'~'~~t'9F PUBI~-~G V1r~K$ f 1 ~11a0.~.~~,r~,~.~1.~~3~- ~
TRAFFIC ENGINEERING DIVISION
TRAFFIC SIGNAL at TANGERINE ROAD/
DOVE MOUNTAIN BLVD. INTERSECTION
The Town is working together with a Dove
Mountain developer to have a traffic signal
installed at the Tangerine Road/Dove Mountain
Blvd. intersection. The signal design phase has
been completed and the Project is currently
being advertised. It is anticipated that the signal
will be in place some time this summer.
SAFE ROUTES TO SCHOOL PROGRAM
The Traffic Engineering Division is in the process of
finalizing the Town of Marana's Safe Routes to School
Pilot Program at Twin Peaks Elementary School. The
Town of Marana's Safe Routes to School Programs'
goal is to develop educational, engineering and
enforcement tools with which to help provide safe trips
for elementary and middle school students on their
way to and from school. Via the Pilot Program at Twin
Peaks a documented process was developed so that
~~ those immediately involved with the program
(Department of Public Works' Traffic Engineering
Staff, police, school administration, teachers and
parents) all understand the procedures and their
respective roles in the process. Town Staff will
continue to work with the Safe Routes to School
Committee for Twin Peaks to implement a safe routes
plan and an educational campaign for the school. The
Committee includes the school's Principal, the
school's Police Resource Officer, the Marana Unified
School District's Director of Operations, and Scott
Leska of the Department of Public Works Staff.
CORTARO FARMS ROAD/HARTMAN LANE INTERIM SIGNAL PROJECT
-~.
r~.
~~
l 'a
~ ~~~~,
°r, 1.
,~,
The Town's Cortaro Farms Road Project, which will widen the road to four lanes with a raised
median from the Union Pacific Rail Road tracks east to Star Grass Drive, involves two phases.
During Phase I an interim traffic signal will be installed at the Cortaro Farms Road/Hartman
Lane intersection, along with an eastbound left-turn lane on Cortaro Farms Road and
southbound right-turn lane on Hartman Lane. This Project, which should greatly enhance the
traffic safety at that location, has been advertised and awarded. Work is expected to begin
within the next 30 days. The design plans for the Phase II improvements are in their final stage
and should be completed by March.
TRAFFIC SIGNAL at SILVERBELL ROAD-WADE
ROAD INTERSECTION (comuleted project)
A traffic signal study conducted at the Silverbell
Road/Wade Road intersection found that the
installation of a traffic signal is warranted at that
location. The signalization will make this a much
safer intersection for motorists exiting Wade Road,
pedestrians crossing Silverbell Road, as well as
emergency vehicles entering the intersection from
the Northwest Fire/Rescue District's Station on
Wade Road. The signal was activated and became
fully operational on 6 January, 2005. Aribbon-
cutting ceremony, sponsored by the Continental
Ranch community, was held on 23 January, 2005.
GRANT PROPOSAL for ACCIDENT DATABASE
The Traffic Engineering Division has prepared a grant proposal to the
Governor's Office of Highway Safety to request funding for the
development of a traffic accident computer database. The purpose of
the accident database is to provide a tool that our staff will be able to
retrieve the accident information needed to effectively conduct traffic
engineering studies. At this time, Department of Public Works Staff
has to spend much time reviewing large numbers of individual
accident reports in order to perform studies. With the database, the
Department of Public Works Traffic Division will be able to quickly
retrieve accident data according to date, time-of-day, location, type of
accident, weather, severity of accident and other pertinent information
that will greatly enhance our ability to analyze accident causes and
recommend corrective measures. The sooner we can complete our
studies, the sooner that traffic safety improvements can be imple-
mented.
~D~P~~~`~~PUBLI!i~ ~Yt~RKS EilQL.UME ~~: T55U~:.,1Y
ENVIRONMENT/~L ENGINEERING DIVISIC3N
TRES RIGS DEL NORTE:
This Study is a cooperative effort between the City of
Tucson Water Department, Pima County Flood
Control District and the Town of Marana in
conjunction with the United States Army Corps of
Engineers. The purpose of this Study is to evaluate
approximately an eighteen mile stretch of the Santa
Cruz River from Prince Road to Sanders Road for
potential projects such as habitat restoration, water
supply, flood control, and recreation.
STATUS: The local sponsors met February 23, 2005
to finalize the draft Recreation and Water Supply
Plans. The Town of Marana is working with staff of
other governmental agencies to develop the best
overall plan for the Town. A 75% product is expected
for the F-5 study around June 2005. The F-5
document is not expected to be 100% until the first
quarter of 2006.
SANTA CRUZ VALLEY NATIONAL HERITAGE
AREA:
The vision of a National Heritage Area designation
for the Santa Cruz Valley in Southern Arizona is
gaining momentum due to a convergence of local
efforts to conserve natural resources and open
spaces; to presence historic structures and
archaeological sites; to educate the public about the
history and cultures of this region; to increase
national recognition of the region; to develop heritage
tourism and bring other economic benefits to local
communities; and to improve cultural ties across the
U.S.-Mexico border.
STATUS: The Town of Marana showed support of
the application and designation of the Santa Cruz
Valley Heritage Area by passing Resolution No.
2003-133 at the Town Council Meeting on October
21, 2003. Preservation and development is ongoing.
SCENIC DRIVE RESTORATION:
Environmental Staff has met concerned citizens
interested in work to restore portions of the Scenic Drive
wildlife corridor.
STATUS: The Environmental Division is in the scoping
stages of this Project. Meetings with local residents and
other interested parties have identified specific areas of
concern.
ARIZONA POLLUTION DISCHARGE ELIMINATION
SYSTEM:
This project was initiated by a federal mandate in which
Arizona Department of Environmental Quality (ADEQ)
was given primacy. Six minimum control measures have
been defined for compliance, they are as follows:
1. Public Education and Outreach
2. Public Involvement and Participation
3. Illicit Discharge Detection and Elimination
4. Construction Site Storm Water Runoff Control
5. Control of Post-Construction Site Runoff
6. Pollution Prevention and Good Housekeeping.
G~~an W ester
.;
w
Cart He~P~
~ STATUS: The Environmental Division of the Town is
~' preparing activity packets for the MUSD school outreach
in March. Grades included are 5th, 6th, and 7th. A total
of between 550-570 children will attend these
presentations in the month of March. We will kick-off our
stormwater pollution prevention artwork contest at the
same time.
The first quarterly report was submitted on February 24th,
along with a request for reimbursement for $14,386.34.
The Town's match for this quarter was $10,271.43,
mainly in personnel time spent on the Projects. The total
amount was $24,657.77. We still have over $20,000.00
remaining in the grant, 95% of which is personnel salaries
on the Town's side, and approximately 85% on ADEQ's
side.
Two staff members attended a NPDES workshop in
Scottsdale on February 21st sponsored by Bentley
Systems and paid for through the grant.
Staff completed data entry of stormwater outtall
information currently known into the StormView module of
Cartegraph the week of February 14,2005. Jack Avis in
the GIS department was very helpful in coordinating this
activity. StormView will help the Town to track illicit
discharge and other public concerns or problems within
the Town, especially once Call Link becomes activated.
.:
ENVIRONMENTAL 'ENGINEERi~tG DIVISION (continued}
PROPOSED MITIGATION LAND
DEVELOPMENT:
The Environmental Division is currently
developing a log and map of the existing
and proposed mitigation lands for the Town
of Marana. The purpose of this Project is to
provide information and support for the
Bajada Environmental Resource Overlay
District (BEROD) and the Town's Habitat
Conservation Plan (HCP) and future
developments within the Town of Marana.
This map will provide information on the
maximum percent disturbance and the
binding agreement that requires the
mitigation.
BERRY ACRES LOMB:
This Letter of Map Revision (LOMB) will potentially
'~ _ _ 'remove the majority of the Berry Acres Subdivision
r;. ~; from the Federal Emergency Management Agency
a.~ ' (FEMA) floodway. The properties will remain in the
'~ floodplain designated as a Zone AE, but will allow for
~ development and redevelopment in the area.
STATUS:
This LOMB is anticipated to be effective March 10,
2005. The Town of Marana is working with the Pima
County Flood Control District and affected residents
for the acquisition of properties that are still located
in the floodway.
SUNFLOWER CITIZEN'S ADVISORY COMMITTEE:
Environmental Staff met with a citizen's group from the Continental Ranch area on January 27, 2005. These citizens are
interested in the creation of a Citizen's Advisory Committee, along the lines of the one that the City of Tucson is now
organizing. This will be a good move, as often, the municipality can get volunteers on these committees who are retired
from a career with years of expertise in an area that is very useful.
STATUS:
This group wants to meet again, along with Pima County department of Environmental Quality-Air Quality Division,
representative to discuss air quality issues in the Continental Ranch area. The group would like to see Marana become
proactive in developing an Environmental Department with enforceable Town codes relating to air quality and other
environmental issues including wastewater.
TITLE 16-EFFLUENT RE-USE PLANNING:
The Title 16 process began several years ago as a
regional effluent re-use planning effort, which was
initially coordinated by the Tucson Regional Water
Council. Title 16 is a funding mechanism available
through the Bureau of Reclamation that offers 50%
Federal matching funds for planning and 25%
Federal matching funds for construction of water
infrastructure projects that meet the programs
criteria.
STATUS: This Project will take much of the
agriculture on the south side of the river off
groundwater, protect water quality in our aquifers,
and provide a reliable, low-cost water supply for the
agricultural economy. We will also have the
backbone of anon-potable supply system on the
south side of the Santa Cruz, which will be able to
supply turf and exterior use if that area urbanizes in
the future. We are currently working with the
Bureau of Reclamation on providing water
consumption estimates for parks and turf areas
along the pipeline.
CERTIFIED LOCAL GOVERNMENT:
The Environmental Division and the Planning Department
are working together on trying to organize the application
for the Town to be designated as a Certified Local
Government (CLG). This certification is through the State
Historic Preservation Office. It requires a Cultural and
Historical Preservation Board to be active in surveying
and inventorying the cultural and historical resources in
the Town, as well as in reviewing development issues
that would affect the Town's cultural and historical
features.
The CLG process requires us to develop an overlay of
the general areas of the Town containing cultural and
historical features that should be considered for
preservation during the planning review process. The
features chosen by the Town to be preserved will
eventually include a historic district and will establish a
visual and tangible lesson on the rich history and culture
of the area for future generations of residents and visitors
to learn about and to appreciate. Certification under this
program would offer the Town opportunities to receive
grant funding for preservation projects in the Town. This
Project is currently on hold due to staff workloads.
_ i
"i~~Jl~Ii~S
ENVIRONMENTAL ENGINEERING DIVISION {continued)
FLOODPLAIN UPDATES:
Number of Permits Processed (February): 5
Number of Flood Hazard Information Sheets Completed:l5 -~
,~
The Town has not yet received the FEMA report on the study conducted by the National Flood
Insurance Program (NFIP) in late August. .-` ~ _ ,.
Four Marana staff members will be attending a training class with the Pima County Flood r
.~_
Control District on February 28 and March 1, 2005 for culvert hydraulics. `i ~',
i
EXPANDED TORTOLITA PRESERVE CONCEPT:
The Town of Marana's Tortolita Preserve consists of 2400 acres. The Town of Marana is looking to expand the existing
2400 acres of Preserve land by an additional 16,200 acres. The Town has started a dialogue with the Unites States Fish
and Wildlife Service, the Bureau of Land Management, and the Arizona State Land Department. This Project would
benefit the residents, the environment, and potentially assist with the recovery of an endangered species
STATUS:
On-going coordination between Town staff and State Lands to see what is a feasible option for acquiring state land for
preservation of open space.
BLM CONFLICT RESOLUTION:
Town of Marana is working with the Bureau of Land
Management (BLM) and various stakeholders on
addressing recreational shooting issues on the BLM,
Forest Service and other Public lands.
Status: Planning continues for the second public
workshop.
HABITAT CONSERVATION PLANNING:
The Town of Marana's Habitat Conservation Plan (HCP) considers six species in total. There are specific strategies for
four of these species. These four species include the Tucson Shovel-Nose Snake, the Ground Snake, the Cactus
Ferruginous Pygmy Owl, and the Burrowing Owl. The conservation measures used in the strategies for these four species
also acted as conservation measures for two additional species, the Lessier Long-Nosed Bat and Pale Townsend's
Big-eared Bat.
STATUS:
The Town is currently in the process of applying for the "year 2" grant form the Arizona Game and Fish Department. The
Town is also working on a planning fair that will provide the audience with information on the Town of Marana's, the City of
Tucson's, and Pima County's Habitat Conservation Plans as well as the land Management Agencies planning efforts that
are ongoing in the Tucson Basin Area. This has been scheduled for March 10, 2005. GIS is involved in the effort as well to
provide maps and help facilitate the meeting.