HomeMy WebLinkAbout06/20/2006 Blue Sheet Water Staff Report
~
.0
r-
Town of Marana
Water Department
Monthly Department Report
May 2006
r'
- -
r'
Water Conservation Tip: Water during the cool parts of the
day. Early morning is better than dusk since it helps in
preventing the growth of fungus. Saves 300 gallons.
--
r'
MAY 2006
CUSTOMER INFORMATION
4322 Number of customers billed
129 Number of disconnects
138 Number of new connects
97 Number of new services with meter installation
58,860,840 Total gallons sold
I"" 92.67 Acre feet pumped for the Airport, Airline/Lambert, Continental Reserve/
Picture Rocks and Hartman Vistas
113.86 Acre feet of wholesale water purchased (Cortaro Ranch/Oshrin, Falstaff,
La Puerta and Marana)
DAILY OPERATIONS
r'
. 360 Work orders completed
. 283 Blue Stakes completed
. 90 Transponders installed
. Installed three new service lines on Hester Dr
. Inspected well and booster sites on a daily basis
. Performed routine water samples
. Inspected all new water construction
. Worked at CAP turnout and at Marana Park's pool
. Stock-piled sand for CAP turnout
. Poured concrete around valves on Sanders and Cerius Stravenue
. Potholed for Operations and Maintenance department
. Repaired leaks at airport and Honea Heights
. Ran temporary line for Wendy's and Chevron for new tie-in on Cortaro Farms
. Assisted Marana School District with their water operations
. Repaired fire hydrant at airport
. Had a person on standby for the month at Honea Heights for new sewer line installation
~~
.--
r'
WATER SERVICE AGREEMENTS BEING NEGOTIATED
. Sanders Grove (Diamond Project)
. Willow Ridge Agreement is pending
. Addendum to Vanderbilt Farms is pending
. Gladden Farms II
. Tangerine Crossing
. Tortolita Mountain Ranch (Ziprich)
. Silverbell Plaza (Steve Mar)
OTHER
. Regional Water Organization Presentation being presented to Councils, Board of
Directors, etc.
. A non-potable Master Plan is underway. Discussions and direction on services to
individual lots with Arizona Dept. of Water Resources underway
. Non-potable system and storage are in the discussion, and draft, design stage, for the east
side ofI-I 0, from Tangerine Rd to the Pinal County line
. Effluent and Marana Wastewater Treatment Plant in discussions with Pima County and
Tucson Water
. Flowing Wells excess C.A.P. allocation transfer in process at Arizona Dept. of Water
Resources
r'"' . Parker Davis electrical allocation
. Modification of Designation of Assured Water Supply in progress
. Service area designations with the AZ DWR in progress
I"
2