HomeMy WebLinkAbout06/21/2005 Blue Sheet Water Staff Report
For: May 2005
~--~
MARANA
~/ 1"
TOWN OF MARANA
TEAM WORK-
Is all staff working together In outstanding ways} with extraordinary cooperative effort
to accomplish ordinary tasks
TO:
Mayor Ed Honea
Town Council
Mike Reuwsaat. Town Manager
FROM:
Water Department Staff
SUBJECT:
May 2005 Department Report Update
DATE:
June 2005
CUSTOMER INFORMATION
55.70
Number of Customers Billed
Number of Disconnects
Number of New Connects
Number of New Services with Meter Installation
Total Gallons sold
Acre feet pumped (non-trust wells) Picture Rocks, Happy Acres, Palo
Verde, Airport, Continental Reserve, Hartman Vistas and Gladden Farms
Acre-feet wholesale water purchased (trust wells) Marana, La Puerta,
Oshrin, Falstaff, Honea, and Cortaro Ranch
(325,851 gallons = acre foot)
3516
127
154
102
49,948,858
110.79
DAILY OPERATIONS
1. 376 Blue Stakes completed.
2. 308 Work Orders completed.
3. Well site painting
4. Sprayed well sites
5. Repaired broken hydrant. Sandario/Marana Rd and installed ballards around
hydrant.
6. Recycled police furniture to Operators office.
7. Tested 2 Backflow preventers and replaced 2 Backflow preventers.
8. Grier Rd Water Main went online crews spent several hours helping out with the
change over. (includes After Hours)
9. Repaired leak on Grier rd.(After Hours)
10. Repaired leak on Silverbell (After Hours)
11 . Replaced meter on Grier rd for mainline project.
12. Installed a new service on Grier in order to abandon a large section of old 6" on
Sandario.
13. Installed service at the airport.
14. Repaired leak at the Standpipe.(After Hours)
15. Repaired Broken Water Main at Hartman and Cortaro.
16. Eagle Scout began painting Hydrants.
17. Construction inspections at Continental Reserve NW medical Center, CR block
17, Gladden Farms phase 2, Hartman/Cortaro Project, Ironwood Reserve, Grier
Rd and Rancho Marana.
WATER SERVICE AGREEMENTS BEING NEGOTIATED
1. Noel Earls, Larry Moore, Shelia Moore and possible John Lashley. Artesiano Rd
off Ina Rd.
2. Oasis Development-Addendum to Hartman Vistas
3. Continental Ranch Parcels 56, 57 and 72.
4. Willow Ridge Agreement is pending.
5. Addendum to Vanderbilt Farms is pending.
6. Northwest Hospital Clinic on Continental Reserve Loop.
7. Payson Farms & Fianchetto Farms
8. Addendum for Saguaro Springs (Saguaro Reserve)
OTHER
1. Discussions of regional reliability and terminal storage of CAP. water being
discussed and presented to the CAP. Board of Director for support.
2. A non-potable Master Plan is underway. Discussions with Arizona Department of
Water Resources.
3. Non-potable system and storage are in the discussion, and draft, design stage,
for the east side of 1-10, from Tangerine Rd. to the Pinal County line.
4. Effluent and Marana Wastewater Treatment Plant in discussions with Pima
County and Tucson Water.
5. Flowing Wells excess CAP. allocation transfer in process at Arizona Department
of Water Resources.
6. As of January The Water Department started billing for sewer on our water bills.
7. Rate model is being updated and completed.
2