HomeMy WebLinkAboutCouncil Executive Report 09/17/2008�'�':� �v �� ;.. � .
. �; a� ,,��*
� � �.
i
9 : � ... , ,,,. . - �,
e s'
Tow�i �������aran5a
:
�,� � ��. � : ,:- . ����.���� � �� �,. �
��: � �: � �
C�� �fc�a�'� ��e�� r� �y'��y .�e��rt
�� �� � : � ... r a �%.
, f S��i��'m��r.,17, ���18 � �'�:.
,�� �� A ;
`. "�' `. ��.ti
� � ��� �
= ,
,: � ;
_ _
� � .� , ��
« ,,. � �
Report Time Period: September 1-15, 2008
Prepared On: September 17, 2008
Prepared By: Rebecca Kunsberg
Distributed Through: Gilbert Davidson, Town Manager
.
�
" � "Committed to the futu�e...
MARANA
/ �� Inspi�ed by ou� past. "
• ORGANIZATION WIDE UPDATES
o BUILDING — PG 2
o CAPITAL IMPROVEMENT — PGS 3-6
o LEGAL — PGS 6-8
o MARANA REGIONAL AIRPORT- PGS H-9
O OPERATIONS AND MAINTENANCE - PG 1 O
o PARKS AND RECREATION — PG 1 O
o POLICE — PG 11
o TOWN CLERK PG 11
o UTILITIES PG I Z
� COUNCIL CALENDAR
ORGANIZATION WIDE:
A. BUILDING UPDATES
GENERAL OFFICE
• All Building Safety staff inembers are signed up for building code training classes third week
of October
RITZ CARLTON RESORT DOVE MOUNTAIN
• Construction is in steady progress.
Attending regular meetings at the job site bi-weekly on Wednesdays.
PROJECT UPDATE REVIEW
• Lasertell has Tentative Improvement in review.
• Monsoon's Grill opening Sept 13, 2008
(July 2008 Building Permit Report attached)
-2-
B. CAPITAL IMPROVEMENT PROJECTS
SILVERBELL ROAD INTERCEPTOR PROJECT: 1999-050
� Concrete spillways for the main channel outlets are complete. Handrails are being installed on
various structures. Grading, concrete, rock slope protection and channel drop structures are
nearing substantial completion overall. The channel `C' low flow channel is 95% complete
while grading continues in the other two channels.
• Of the main drainage structures under the roadway, box culvert #1, is complete; #2, is
complete; #3, invert poured, wall and deck forms started; #4, is complete; #5, is complete;
#6, triple Reinforced Concrete Pipe (RCP) installed; #8, is complete; #12, single RCP 50%
installed.
• Curb and gutter has been placed along the east side of Silverbell Rd. from the start of the
project to Bradstreet Dr. Two lanes of asphalt concrete have been laid and traffic shifted.
Earthwork is progressing from the north end of the project to Bradstreet Dr. along the west
side. Ditch cutting is in progress throughout the project.
• The sanitary sewer is complete from the existing manhole to manhole #10 including laterals.
Two runs and two manholes remain. The potable water main and joint utility installations
being approximately 90% complete with remaining work in progress along Ina Rd.
• Exploratory archaeology work is on-going in the park area adjacent to Silverbell Rd. The
park construction has received DEQ approvaL
• An anticipated 25,000 cubic yard shortage of fill material is being imported in stages as
suitable material is identified and tested. Ina Rd. has been detoured to the south of the
original intersection so as to open up the proposed intersection area in its entirety and
accelerate the work. This shift will allow for approximately 85% of Reinforced Concrete
Box Culvert #7 crossing Ina Rd. to commence outside traffic lanes and the installation of
permanent traffic signals. Existing Ina Rd surfacing has been milled and embankinent has
commenced.
• At the end of August, 45% of the completed construction contract work based on total cost
has been spent. To date, 65% of Phase I construction time has elapsed.
• Value engineering, environmental concern monitoring, testing, quality control and assurance
are on-going daily. The project has had no reported safety issues.
• Based on a revised schedule (Sept. 8) submitted by the Contractor, the Phase I opening to
Silverbell Rd. traffic may occur from early to mid November. Finishing roadway
appurtenances will continue through February. Review of alternatives and options.are
ongoing to reduce construction time and costs.
THORNYDALE ROAD PROJECT:
-3-
• The project is approximately 79% complete. Substantial completion is expected by mid-
November. Autumn weather permitting, the project team is working toward placement of the
final lift of rubberized asphalt in calendar year 2008 ahead of the original schedule which did
not have this phase of work occurring until Spring of 2009.
• Orange Grove is now fully open to eastbound and westbound traffic. Operation of the
permanent traffic signal system at the Thornydale/Orange Grove Intersection is scheduled to
start up by mid October to coincide with the partial opening of southbound lanes on
Thornydale and River Roads.
• Work is underway at the northwest quadrant of the Thornydale/Costco Intersection following a
switch of traffic on September l Oth. At-grade reconstruction of this intersection is now
scheduled to be complete by September 24th.
• In order to expedite construction of the Thornydale/Horizon Hills Intersection, planning is well
underway for its full, ten day closure beginning September 24th following completion of the
Thornydale/Costco Intersection. Special access will be given to businesses located in the
northwest quadrant of this intersection while this accelerated work occurs.
• Along the west side of the Thorn�dale mainline, base paving from Orange Grove to Costco
was completed on September 11 `. Work on sidewalks and access ramps within this segment
is occurring. Cement treatment of the roadway subgrade, finish grading of aggregate base, and
installation of concrete curbing is underway north of Costco Drive to the CDO Wash. Base
paving of this segment of the roadway is currently scheduled for September 22 & 23` As
has been customary for the project team, providing access to businesses particularly affected
by any ongoing work is a prime consideration.
Ongoing public and business outreach remains an important part of the project.
Communication efforts to advise area businesses about the status of the project continue with
the goal of such information helping minimize inconveniences to their operations and
customers. A specific focus of the project team is in regard to the expected large scale traffic
impacts that will occur in October when the final lift of asphalt is being placed within the
entire project area. Other focus is being given to recent, incomplete media reports
characterizing the project as having an overly adverse impact on certain businesses. Also, as
part of the public and business outreach program, early stage conversations have begun toward
developing the scope and schedule for a concerted roadway grand reopening event.
• The project team remains engaged in an impressive partnership, fostered in part by the
construction management at risk contract delivery method, which is reaping dividends in terms
of both schedule and cost.
THORNYDALE RD. / TANGERINE RD. INTERSECTION IMPROVEMENTS:
• IGA with the RTA was approved by the Town's Mayor and Council and wili now go for final
approval with the RTA on October 23, 2008.
• Estimated to begin construction the early November 2008.
-4-
• Duration of construction is anticipated to take 3 months
TWIN PEAKS PROJECT
• Conditional cultural clearance obtained, there are areas of further recovery that will need to be
cordoned off from construction initially.
• 404 permit comments being returned to corps again
• Final right of way being acquired. UPRR easements payment sent to UPRR. Final
condemnation hearing first week of September. Working with legal and title companies for
east side dedications
• UPRR C&M agreement signed. Meeting before Arizona Corporation Commission set for
Camino De Manana closure
• Demolition begins September 2.
• Prospective bid of October, 2008 still possible
TANGERINE FARMS LOOP ROAD:
• Punch list, site cleanup work, and project closeout in progress
• Drainage along Street A into Cemex pit negotiated with Cemex, design and construction
modifications to follow
• Signalization of the I-10/Tangerine Road intersection: site electrical work substantially
complete, signal cabinet being checked and prepared by ADOT, awaiting delivery of poles for
installation to energize signals, currently expected in September, 2008
HONEA HEIGHTS WATER, SEWER AND PAVING PROJECT:
• Paving was completed in July, utility adjustments and site cleanup is in progress
• Two additional sewer manholes, sewer main and service connections installed for low income
housing project on town owned property on Whitney Ln., in new road alignment for Sydney
Place
• Sanitary sewer as-built information is being compiled for submittal to Pima County Waste
Water Management Department and Arizona Department of Environmental Quality (ADEQ)
for final Approval to Discharge, to be submitted after final manhole rims adjusled to new
street pavement elevations and final survey information and post paving inspections completed
• Connection of homes to new sewer main to begin after Approval to Discharge issued by
ADEQ, program currently calls for approximately 200 homes to be connected over a three
year period. Bid documents are in the process of being developed for the first phase of this
work.
• Sidewalk construction planned once all homes are connected to the sanitary sewer system
-5-
CAMINO DE MANANA PROJECT
• 404 permit application has been submitted to the Army Corp, Town staff is expecting approval
from the Corp in the next couple of months
• The Town sent out consultation letters to several Tribal governments regarding the Cultural
Resources Survey Report for the Project. No significant cultural resources were found, and no
issues are expected.
• Right of way acquisitions are currently on going and are expected to be complete by January
2009.
• Project is anticipated to begin construction early next year which will last 12-14 months
BARNETT LINEAR CHANNEL
• The FEMA in-flow water has been received and is being analyzed by the CIP Engineering
Division. The results may indicate that the channel can be reduced in size, thus allowing for
the reduction or elimination of TEP line relocations. This analysis will be finalized by mid-
September.
• Existing underground utilities have been located for design of the utility relocations within the
Rail-Road rights of way. The results will be submitted by the first week of September.
• Environmental investigations for bridge foundation geotechnical investigation coring have
been put on hold until the farm fields within the Town's Right-of-Way are harvested. The
approximate date for harvest is December 2008.
PAVEMENT REHABILITATION PROGRAM:
• The 2007-2008 programs have been finalized and are complete. The 2008-2009 is underway
and the remaining residential streets within the Sunflower neighborhood are being advertised
for bid and work is expected to begin late September 2008.
• If funding is available following the Sunflower pavement rehabilitation, staff will look into the
costs of rehabilitating Twin Peaks Road between northern Silverbell Road to the Saguaro
Springs development.
• Engineering staff has met with pavement specialists to look into the possibility of using
recycled materials for the Twin Peaks Road over the Rattlesnake Pass corridor. This
potentially may reduce the costs of rehabilitation of that section of roadway.
C. LEGAL DEPARTMENT UPDATE
WASTEWATER LITIGATION
• On August 29, Marana filed the last pleading concerning its request for final judgment on
Judge Hoffinan's June 9 ruling.
• On September 15, Pima County filed the last pleading concerning its motion for
•reconsideration of Judge Hoffinan's June 9 ruling.
�:�
• Unless Judge Richard Mangum sets oral argument on one or more of the pending motions, a
ruling could be issued any day now on Marana's request for final judgment and on Pima Count�s
motion for reconsideration.
WASTEWATER TRANSITION
• On September 5, Marana sent documents to PAG explaining Marana's objections to Pima
County's Regional Optimization Master Plan (ROMP) Section 208 Plan Amendment (the
planning document required by the federal Clean Water Act to ensure appropriate planning
and treatment of all regional wastewater).
• On September 8, Marana staff presented to Pima County staff an overview of Marana's
proposed Section 208 Plan Amendment, addressing Marana's treatment facilities planning
alternatives.
• A September 18 meeting is scheduled between PAG's attorney, Thomas Benavidez, and Frank
Cassidy to discuss Marana's objections to the ROMP Section 208 Plan Amendment. Members
of the Pima County Attorneys' office have been invited but have not yet responded.
• A September 29 meeting is scheduled between Marana and Pima County staff to identify and
describe the wastewater conveyance infrastructure located within the Town of Marana.
CMID IGA NEGOTIATIONS
� A draft IGA has been prepared to facilitate the use of hydro-power at three CMID wells used
by Marana for potable water deliveries. �
� On September 11, the fully executed Second Tolling Agreement (approved at the September 9
Council meeting) was hand delivered to CMID.
• Meetings have been taking place between the Town and CMID on a proposed IGA to replace
the 1997 IGA. Negotiations are currently anticipated to be completed in mid-November
DEANZA REFERENDUM LITIGATION
• We anticipate receiving a proposed draft stipulation of undisputed facts from Plaintif�s
attorneys any day now.
• Motions for judgment based on the undisputed facts will likely be filed within 30 days
POLICE DEPARTMENT PERSONNEL MATTERS
• Jane has been providing coordination and oversight with respect to the following:
• Barbara Harris' PARB hearing
• The internal investigation being conducted by Lia Keller regarding the hostile work
environment complaints of Harris, Ochoa and Garbini
• The internal investigation being conducted by Merle Turchik regarding the complaints
received from Sgt. Ochoa's "subordinates."
PUBLIC WORKS PROJECT PROPERTY ACQUISITIONS
• All necessary Twin Peaks/Linda Vista interchange right-of-way should be obtained within 30
days either through completion of settlement negotiations or by obtaining immediate
possession in condemnation
• One or more settlement proposals on the remaining pending Thornydale Road/CDO-Orange
Grove condemnation cases are expected to be presented to Council in the next 30 days
-7-
• Appraisals and property acquisition negotiations are in process to obtain right-of-way needed
for the Camino de Manana project
OTHER NOTABLE CNIL MATTERS
• On September 5, legal staff participated in a meeting with Marana and Union Pacific
representatives to discuss proposed deal points for an anticipated double-tracking agreement.
• Saguaro Ranch historic aceess easements are the subject of litigation brought by Theresa
(Tracy) Chamberlain and others against the developer '
• On September 2, Judge John Davis denied Chamberlain's request for reconsideration of the
August 12 order denying injunctive relief regarding the public's rights to use historic
easements through Saguaro Ranch.
• On September 4, Chamberlain's attorneys requested the Town Attorney to sign an affidavit
concerning whether Marana had "abandoned" the public easement (the affidavit is not yet
signed)
• Cedric Hay and Kevin Kish met with representatives from the Arizona Department of Water
Resources and the Arizona Department of Real Estate regarding illegal subdivisions along the
Dove Mountain extension.
PROSECUTION ACTNITIES AND AUGUST 2008 STATISTICS:
• The Legal Deparhnent prosecuted and closed 136 criminal cases in Marana Municipal Court,
including 11 petitions to revoke probation
• The Legal Department accepted 106 new cases from Marana Police Department and other
state agencies for future prosecution
D.1IJIARANA REGIONAL AIRPORT
FIRE PROTECTION WATER LINE
• Under contact to Sundt Construction
There have been no major issues with construction
Construction is 65% complete
SEWER LINE
• Under contact to Sundt Construction
• There have been no major issues with construction
• Construction is 60% complete
SEPTIC TANK
• Design is under contact to Westland Resources
• Design is 50% complete
• Field samples were taken to be analyzed
BY-PASS APRON
• Design is complete
• Construction bids were opened on 8/11/2008
-8-
• Apparent low bidder is Borderland Construction -$763,435
• Award for construction is on hold waiting for ADOT Aeronautics approval
SE�CURITY FENCE
• Design is complete
• Construction bids were opened on 8/11/2008
• Apparent low bidder is Orta Fence -$246,877
• ADOT Aeronautics gave approval to award the contract
AIRPORT ACCESS ROAD
• Design is complete
• Construction bids were opened on 8/11/2008
• Apparent low bidder is Borderland Construction - $1,717,555
• Construction Contract has been received from Borderland and is being processed by the
Town
AIRPORT TERMINAL
• Under design to Jacobs Carter Burgess
• Schematic design is 61% complete
AIRPORT CONTROL TOWER
• Site Study is under contract with the FAA
• FAA draft study and the Airport Facilities Terminal Integration Laboratory visit on
11 / 17/2008
• Continuing to work with Gabrielle Giffords for construction funding
• FAA will visit Marana in October for site study
AIRPORT OPEN TIE-DOWNS
• The Town is taking over the management of the open aircraft tie-downs at the Airport
• Billing methods are being established
� Open tie-down permits have been sent out aircraft owners
AIRPORT HYDROPOWER
• The Airport and the Water Department are working on converting power usage at the airport to
hydropower
• The departments are also looking at past electrical usage of the airport leaseholders to
determine if they may be a candidate for hydropower
• A meeting was held with Airport Leaseholders and the Town on 9/4
STATE LAND - ACOUIRE RIGHT OF WAY
• The Airport has submitted an application to State Land to acquire utility and roadway right of
way to the west of the airport
� State Land has received the application and it is being processed
�
ALL GIRLS AVIATION DAY
• On September 21-22 the Marana Regional Airport will be helping with a Girl Scout Aviation
Badge Program. The Airport will help host an overnight event at the Pima Air Museum with
the Tucson 99's (an all women's organization)
E. OPERATIONS AND MAINTENANCE UPDATES
KEY INVENTORY
• Have received responses from all departments.
• Will be going through all responses to check for appropriateness of keys, OK forms and
forward to HR for personnel file.
• Will complete Phase 1 of access/security issues and begin Phase 2 which deals with well sites
and other security challenges
F. PARKS AND RECREATION UPDATES
MARANA CULTURAL AND HERITAGE PARK
• Punch List Items are being addressed
• Entry monument is in process
• Marana Heritage Park Rail Road — test runs and final adjustments are being made.
• Marana Fall Festival at the Heritage Park being planned €or October 25.
SILVERBELL-CORTARO DISTRICT PARK
• Installation of private sewer for park has begun.
• Archaeology data recovery is being completed:
• Boxing of 12 specimen Ironwood Trees on the site has begun.
CONTINENTAL RESERVE BALL FIELD LIGHTING
• Lighting design in underway.
• TEP is coordinating power delivery with design engineers.
TORTOLITA MOUNTAIN TRAILS WILD BURRO TRAILHEAD
• Engineering plans have been approved.
• Coordinating bid date with Ritz Carlton Construction.
ORA MAE HARN PARK IMPROVEMENTS
• New benches being installed.
• Restroom plans are under review.
PARKS AND RECREATION COMPREHENSIVE MASTER PLAN UPDATE
• Focus groups with community leaders, service providers, and users were held September 15
and 16. Over 35 participants were interviewed by the consultants.
• Phone survey of 400 Marana residents completed.
-10-
RE CREATION
• Cardboard Boat Race, Breaker's Water Park was held September 6. Community interest and
partners is growing and this event will become an annual effort between the Parks and Recreation
Department and Breaker's Water Park.
• Movie in the Park, Continental Reserve Park, September 13 had 200 attendees.
• Itty-Bitty Open (toddler gol fl, The Practice Tee and Continental Ranch Community Park 9:00 a.m.-
12:00 noon, September 27.
• Youth Programs — 4,516
• Teen Programs — 512
• Sports Programs — 45
• Seniors — 1,469
G. POLICE
UNION PACIFIC CROSSING ACCIDENT REDUCTION ENFORCEMENT (CARE�
• Special detail deployed to assist with Union Pacific on Sept.l l,
• Objective was to enforce grade crossing laws in order to reduce collisions and reinforce driver
behavior at grade crossings.
• Twenty-one stops for violations and nineteen citations issued
• News media on board train and on crossings to photograph violations
TIP A COP TEXAS ROADHOUSE SEPTEMBER 2 200H
• Team effort between Marana PD, Pima County Sheriff and Oro Valley PD, benefit for Special
Olympics
� Officers and Command Staff from three agencies waited on tables for donations
• Approximately $3200 was collected between 4:30-9pm
POLICE OFFICER RECRUITMENT TESTING SEPTEMBER 6. 2008
� Thirty-five applicants tested for vacancies within the police department for a future PCSO
academy in February 2009
• There are four recruits from the previous testing that are scheduled to begin the Pima County
Sheriff's academy on Sept. 29, 2008.
• We currently have seven officers and two sergeant's vacancies.
DIRECTED TRAFFIC ENFORCEMENT
• On Tangerine Farms
• Thornydale in the construction zone 126 Traffic Stops in August
DUI TASK FORCE DEPLOYMENT 29 & 30 AUGUST
• 73 Traffic Stops
• 50 Citations Issued
• 9 DUT Arrest
-11-
DIRECTED ENFORCEMENT CDO WASH AND SANTA CRUZ RIVER, 6 SEPTEMBER
• 30 Contacts
• 8 Citations Issued
• 1 Warrant Arrest
H. TOWN CLERK
NOViJSAGENDA UPDATE
• Software customizations finalized by August 29
• Software went live on August 28
• Management, Dept. Head, and line staff training to be completed by September 5
• Council training to be completed by September 9 or at their request
• Parallel testing to occur for Sept. 16 and Oct 7 meetings
• To go live by October / November
C�W & MA�NA 1 O1
• CREW to start September 3 and Marana 101 to start September 4
• CREW will run for 8 weeks and Marana 101 for 10 weeks (1 wk of community partners, 1 wk
of Town tour)
• 34 currently registered for CREW
• 33 employees and 2 commissioners registered for Marana 101
ELECTIONS
• May hold another voter registration drive in September
• Candidate packets for 2009 election being prepared — will be ready after September 3.
• Jocelyn will review elections, publications & deadlines with Sr. Management in Sept.
I. UTILITIES DEPARTMENT
WASTE WATER:
• The Town of Marana is submitting its request to be a Designated Management agency to PAG.
• This is crucial in our quest to be a regional wastewater provider. Deparhnent personnel will be
working with Pima County personnel on transition planning in the coming weeks.
CMID:
• The Utilities Deparhnent and others are actively engaged in coming to a mutually beneficial
resolution with members from CMID.
DEVELOPMENT:
• Several developers have met with the Utilities Department staff over the past week.
• These developers may be seeking to take advantage of possible lower construction costs to get
critical infrastructure identified and in place in the coming months.
(July 2008 Business License Report attached)
- 12-
�
0
Permit T p
New Single Family Residenti
Remodel/Addition SFR (RA;
Manufactured House(MANSI
New Multi Family Residential
Remodel/Addition MFR (RAI
New Retail Commercial (NE
Remodel/Addition RC (RARf
New Industrial Commercial (
Remodel/Addition IC (RAIC1
Swimming Pools/Spas (
Signs (SIGN)
Certificates of Occupanc
Te mporary Construction
Temporary Tents (TEM
Revisions
Mod Plan Revi (M
Plannina/Enaineerina
Totals
TOWN OF MARANA
SUMMARY OF CONSTRUCTION ACTIVITY
�
August-08
Permits Issued
' Number of ;
� Permits ; Permit Fees Valuations
76 $279,782.13 $9,872,800.1
_j 5 $1,391.33 $34,557.00
0 i $0.00 $0.00
0 $0.00 $0.00
� � - $0.00 --- , - $0.00 -
8 ' $39,665.10 $2,254,264.22
3 $19, 014.92 $1, 207 000
0 $0.00 : $0.00 ----
� 0 $0.00 ; $0.00
5 $1,220.56 $40,000.00
9 $3,252.31 ---- -- $85,502.80 --
-
--
9 $3,052.15 ' $
3 ' $135.00 $0.00
; 1 ' -- $290.00 $0.00
� 0 ; $0.00 � $0 .00 ----
-- 3 0 - � $2,820.00 _ _ � __ $0.00 -_ --
0 $p.00 $0.00
+- - - '
23 $9,623.64 � $0.00
; 32 , $6.562.31 , $231.318.52
204 � $366,809.45 ; $13,772,411.67
. .• . .• . .� • � �• ,�
� fi �€ f'3 " � r � ��. F � � � ���&� � �{�€ � � � �.� � ^c m. c ' � \� `�i
�.._..�...��. `�..,,...v�.b � a_..,._,. �.,...�`� _,, e�w ��._....,...._c ' ,..,.....�. ......_.w..,- Ar v_ . -a_ ��..�.���.'��a.��. _w.� . .`,,,�,���;,R
a._.�..�.�
' � . � • . • • ' � . 1 1
Park Impact Fees = 17 units
Sky Ranch Education Fee = 0 units
Pro'ect Name
Park-N-Shade III 8� IW 60601-059
Tang-Xing Pad 4 Shell/60608-128
Starbucks/B0609-0
Affordable Fence/B0711-075
Ritz Carlton/60605-187
McDonalds/B0803-056
Ritz Carlton Clubhouse/60703-137
Shell Pad 'B' Marana Mkt PI/60611-083
Cont.Ranch Shell/60707-097
Shops at Thomydale Shell/B0704-080
Old West tndust Village/6034-191
Ritz Halfway House/60707-093
Shell Enterprise Rent a Car/B0709-079
First Choice Autobody/60801-065
Ritz Swim & Fitness/60707-094
Total Collected = $52,025.00
Total Collected = �0
Status of Current Commercial Projects
% Complete Project Name
80 IShell Marana Mkt PI U60804-066
30 �Shell Marana Mkt PI K,/60804-067
80 �Shell Marana Mkt PI H/60804-068
45 _ � Shell-Chuy's/60806-117
40 � Steak Out Rest & Saloon/6080&117
5 ; Ritz Carlton Casita 1/80707-028
� 75 ; Ritz Carlton Casita 2/60707-027
85 ; Ritz Carlton Casita 3/B0707-024
35 ! Ritz Carlton Casita 7/80707-029
10 ! Ritz Carlton Casita 8/60707-025
85 ! Ritz Carlton Casita 9/60707-026
25
20
30
0
�
m
m
�
0
0
0
� 1
� 1
ete
Cowica Reroxti Calennax
• 1 2 3 4 5
�`': 8 9 10 11 12
'�+�: ; 15 ic 17 18 19
� ���: 22 23 24 25 26
�$ ° 29 30 31
• Sercemsex 16: Re�w.an Cowicu 1lieecm�, 7 rm.
• Serzemseg ZK-26: Goyexnox's RwtaL ConFexence
• Octosex 3: Szate oF ixe to�en oF Saxuaxna
• Oc�osex 7: Re�tiaaa Cowica l?(eetm�, 7 r.m.
• Octosex i�: Szwv Session, 6 rm.
� Oc�osea 21: Re�w.aa Coirnca l'tteeim�, 7 r.m.
• Oc�oseg 25: Hegna�e Pestnai 9 a.m. to K r.m.
• Oc�oseg Z8: Stiwv Sess�on, 6 r.m.
• Oaosex 31: Sroox�acw.ag @ Oxa lttae Xaan Paxx
• nOYeMB6R �I Genesai elec��on
� llo�emsex 5: (�Qe�nesuar) Re�w.ax Coirnca ytteetm�. 7 r.m.
• lio�emsex 11: Yetegans' Dav-toxn o��ces closen
• l]opemsex 18: Re�w,ax Co�mca liteetm�� 7 r.m.
• llo�emsex Z7 & Z8 txanxs�m� o��ces closen
2009 Da�es
• Fesguagr 25-7ttaxcx L• PGA �OUR Accent�e �'lazcx PLaY Cxamrionswr
• niaxcx Zi: Fotiowegs' Dav
• Arxa 30: Stiate oF zxe toxn
• Decemsea 2: Re�iaax Coimca �'leetm�, 7 ran.
• Decemsea 6: Cwus�mas taee 1��m� Ceaemonv.
• DecemBex 16: Re�w.ax Cowica lfleetmw 7 r.m.
• Decencseg 25: Cwuscmas DaY-toxn o��ces closeD
n�� p��� o� W 2 2 D p ���� D��� z c�� n W m n D�__�� n� W D� m z
0 o v m� o m v p O v� c m m� c � v � m��� m m� o v o p m v v� a v��
= a o' � a� � �n ,� o �� o- m v, �n m� c� � � g � rt v �` x cn X� � 6 � � v �� n�i c� � �
v�i � � � � v c� � � � cn m o �. m v' � _ � D �- r a �' �p• � � v � � o m vsi m • `� m � � v, �
rrt o v Sp ° � m .� D �' = Z � �' � �• o °� � � � � � m � C < W fD o � � � D n�i � � m °- � c�o
x� a n � v � o v, 2 o CD v� m � n�i � m�. oo �' v Z�� cn v�� y� ����� D a� cn �
< � �° c� v� o v � v�i � o�� �� v� �� S. m�. � o o D cQ n�i r ' �°' �° j � o o���' �
��.a� 6QO Ov�� ��� o �spa� � u m�D° �o n=•m c �c� m y� o� v m
�o � � ��' o� c�n fp c �� �' c�n n v � v � o � � � � n � vi �� m �
r v � 3 p C� C� v�i c�� n o r a• Q> > c � C� � n r 3 � p �
n �' o � � ° � ^ . � � c'n n n ca c Q � � � o r � � °o - a
cn - �� � N �<i o� C
�' r c
c r n -. N �� � j � o � � n o.� cn
n o � � �
� 3 �
c�
v
�
d
�
m
m
v'
�
�
�
n
N
7
m
0
�
v
v
�
v
C� fl-
O 6
7 �
� D
� �
o �
� �
� `u
� :
�
(D
�
�
m
�
�
�
2 �
0 �
�
� �.
W
� Q°
� �
� a
� �
�
�
Z
d
7
to
a
a
���� o v�� a�i o m�- � a, W�D m � v� v � 3 c � s°c � m��� � m o m� v o v� m� o
� m� ?.0-3 o x-,,� o < •� � m�c < a s� •—�.�
v�� m � m 3 Z cn �� � a� � s r - v' ' m a��'� - �� a a�� o: Sp m�• m�' � o m.� �' �� r►
m m°� � v m �. m� m n p � G� > j� m m�� � m c�i ai � v m D cn T ��� y � oo v o��
� r�0o��' m o �rv a -, � � W nC)p� Q v
n po m,� o o�- o� m 3� vi ���� 3 m m o Z� �� i� � �• �°� � � � v°�� m n po y
0 o ci � �� � o m m� � � m �- � s� o
7 a y � � < � `< � CD (n j � � !�/7 fD j � 3 C7 � n p�j . � CD � � � j � (p 3 � 6 y � p � (p �
(/� _� p_ 7 C� O_ j' IV p N O CD < d S � -ti fD � � O��
co m� v ��° m v p� y 3
C fD IV � � � N � � � (p �
� �
�
n
CJ� CJ7 CT �� CT7 A Ut (1i Ui W N OD U� CI7 � CI7 CIt . U� (n � Ut �CT C.7i CJ7 CT N Ui CJ7 CJ7 U� C.)i ��� CTi �� CT� U7 C7� CT � 3
N N N N O N OD N N N-� -� C7� N N O N N N N O U7 N N N N N? N N N N N O O N O O O N N N N,,,�
O O O� N O O O O O W P OD O O N O O O O N N O O O O O OD O O O O O N N O N N�� O O O� p�
�1 A N U� N�I � A N�1 W CJ7 �I C77 CJ7 ?�1 J� CO N N O�1 6) �I �J A U� ? N CO CJ� CO � CO A CJ7 W 00 00 N� CI7 �
N C4 ? 00 U7 00 CO CO (O �P U7 A CO �I N� A N�P V� A N 6) 0� A N CO O V O�I �l (O 1� CO ? W�I �� O��
� O Ui N O> O U� O(O U� A N W? Gfl CO Ui A O O CO O-� 00 O W(O �P O C7t CO N�1 N A 00 O CO �I � 00 CO � S
i i i i i i i i�� � i i i� i i i i� i i� i i i i i i� i i i� i i i i
�I �l �� O��I N O O O W tJi N N W W CJ� O CJt � O�I OD � 00 W W O) N CT (O O 00 N��l Ut N Cfl (O � CO 0
00 W CIl N(D t0 Oo --� (O 00 O� W? 00 W Q� CT N A N C4 ? 00 00 �l ?� Ut O W O�P ?�� CT O�� O�I O�
A�� 6� C77 O 00 Ui C7i 00 O� O��l 00 O W�I (O O� W N CJt ? CO A 00 O GO Ui A�l W CO N N? O��� 0� �
N O U7 N� O����1 CO �1 CO N CT N O W�1 �I W CO W Ut 6) 00 W OD QO W�(O Ut W� 00 CO O O U� � Ut 00
� � � -- � • � co � cn � 3 � � v, �• � c a� _ � v � � �• �� � s � 3 �
-h o m m m� � � v � �� m �� v v�, 3 � m
o� fl- < 3 0 0 0 � o �� v� m��. �� v �� � ( ^ o � �� � - o� 0 3
o a � co m� 3 cn m � o � ni ?� � c� �n Q� � m m m� �� m n�• �
� Q � `� 1i�1 \V � \V � � 1
- ° / m �n � v � � ^ 3 � nP � m ` s (� - � � � 3 � o -� v �• � n � �
V> � 1r� %� O N N:+ � lCJ fp � <p N `� N�p �. �. p � fD � a j �. O Q � 1 � `�
� � fl- ` � ' C���m o�- C�m y� v�� �•�� Q" 3 Qc��o n'i(�� o o
v 5 0 � o a� ^ � r ° v m �� � m o S v cn 3 �� ^ �� � � � � ,� x
N n C� O N n 1�J �� 0 � � N �� N O 7� � � `� � N G X n � O�
lC/ � x o �n o v.� v 3< co � ,..• 3� o � v �� v m � �� o v�
� 3 � ' � v' 3 ° o o �D � -° o nP � �' �� cQ � � 0 3 � o o � � � (� �
3
� � ° � o° � �� v o � N° o ° 3� � m°
� 0 3 � 3°� �. 0 3 0 � 3 3 � ��
� 3 3 3 3 0 0 � ��? o
0
o � � � �
3
� W� Ui CJ� � W�J � W N O) N Ui A�J ? 0� W W N-+ ��� N 00 W CT (O � 00 N OD (O �� Cfl 0� ��l W W D
CO N CO W W N W��J O� N N�l N W 6� U7 A O� � 6� N N� 00 N U7 �I Ul N� A N W�l O�� 00 -• � fl,
�l 00 N.p � N CT V N N O N A?--� ? N� U7 00 N W N CO 00 N 6) ?? CD W W O� N Ut O O N�(O O Q
CO O� CJ7 � O� W CO � O�l W 00 � CO A�I ��l 6� CT7 A O W 00 O A�I W C77 O -• O� O� N� O��
m�z�g"z�m zz��y
o � m o��� p 3 v�� D v v� o �� o � � o W-� o n o ��� ���• � a�i o�� n�i � �� y
a 3 co m �n � ��. 5 ' m c� o v °' i �� •� s o o � �� m c� m���. m� v ��°. <°
� ° v' � ° c � m �. m °' � o � �. �D v' °' � -< D �' a � m � o � �' � � a � � D � � r ' �. � �' �
v� v� �n � 5 D C� � v o� m m < a � � o� p o m < o cn �� o �' � c
`� Q'��Dj pco �� � < v pv =�. o � �� �p�v m -0� � �o Z °� �
���J� �n cA� �� � �� �� �p ,� �vi -I�p�� � y mc °;.c�i 0
o� o � ° cn o �- �
� v o � � � � � �, o � � -� c� �
� � n o o � � �
� � v �
m
�
0
w
�
w �
�
N
U�1 N
� o
N
�
�
� � � � �
� (D fD p CD
w � o p
� � �
D
a
a
A
W
W
r
�
m
N
� � � G� G� � C) � -I -i � � -I � � c/) � � � -I � c/) � � � -i � � � -I -i � � -I � � � 'O D � -I � � n
!�N l�i) V�i 7��� C�i C�'> C�') C�'> n n n n O C) n C�i C�') O S n n� C) C) n n C�') n C) A� O n O O� n C�'7 � p.0
O O O N Q j a O O O O O O O O� O O O O j p�j O O� O O O O O O O O� j O j pj � O O 7�
7 7 7���� 7 � 7 7 7 7 7 7� 7 7 7 7 X• � 7 7 N 7 7 7 7 7� 7 7� X• 7 X• � 7 7 d X.
� � � � C
CD
NNNNNNNNNNNNNNIV NNNNNNtV NNNNNNNNNNNNNNNN�NNNtVd
l�D
00 00 00 00 0o N Oo 0o W o0 00 00 00 00 00 00 00 00 00 00 0o Oo 00 00 00 00 00 00 0o W o0 00 0o w o0 00 00 00 00 00 00 00 0o N
Cn cn cn cn Cn cn cn Cn Cn Cn cn cn cn cn cn Cn cn cn cn Cn Cn cn v, Cn Cn Cn cn cn cn Cn Cn cn cn cr, Cn cn cn cn � Cn Cn cn cn �
�I �1 �1 W W � N �1 �1 V V �I V �I �1 N V �1 �l �! O � �I �1 � �1 �I �1 �1 V �1 �I �I N O �1 O W � �I �I 6� O
O W� O � W CT W N j�� N� 0� 0�0 O W C�17 W C�D C4 C�O � W C�Jt W fT� C�)i v� W CO N� A� W W 00 W 0�0 V
�
S
O
3
<D
Ut Cn CT �� Cr ? Ui C.7� CI7 W(O (r C1'i Ui � Ut Vt CJi C77 � U� (T CJ� C77 U7 Ui Cr C.)i Ut CT (P A� CT �� U� Ui Ui U7 O)
N N N N O N N N N N��I N N N O N N N N O N N N N N N N N N N N O� O N O O O N N N O
O O O v N O O O O O V N O O CO N O O O O N O O O O O O O O O O O O N O N N v O O O N
� �. � ....�� �� ..�� .� ._.� ... ..�� �.
�1 00 N CP N�l Cn W N�I 00 N W U� U� CO �I ?(O Ut N� J Ui �I �I A? N GO fT �1 �I CO � Ui W W 00 N� CO
N 00 A 0� (.J� N A O C� �P Ui A N�I CO O A N J� -� 6) N(O �I OD ? O O�I O�I A W A CO ? W�l � A O(O
��l CT N� O U7 O�O C7t � W�I ? N? Cn A O A�O fr CJt A O W OD O Ul �O N W�? OD O�O �I � 00 �O �O
�I �I �� O�� O O O O N CJ7 N N Ui W GT O 00 6) �I CT �� 00 �� N Cn CD (O O N��I CT7 N CO CO � W
00 � CT7 W CO (O 00 W� 00 O�� A OD Ui � Ul N N N� CT CO 00 �I CO CT� O W O� N�� CJ7 O-� -+ O�I ?
? O�� Ui O 00 � Ui 00 W O��l 00 (D W�l CO O�� O C4 ? CO O O CO Ui A-+ W CO N N A O��� O
N� CJ7 N� O O Ui ��I� CO O Cp N CJ� � O W�l O W� O CO � W O W A� CO -' Ui � 0� CO O O CT � fT Ui
N N N N N N N N N N N N N N N N N N N N N N N N N N N N N N N N N N N N N N N N N N N N
O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O 61
O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O,1„
OD 00 00 W OD 00 W 00 00 N OD 00 W 00 W 00 00 OD 00 W 00 00 W OD W 00 00 W OD 00 OD OD W 00 00 00 00 OD 00 00 OD 0� W 0
O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O�
00 00 00 0� 00 W 00 W 00 N OD 00 W 07 N 00 00 � 00 N W 00 00 00 N 00 00 W 00 00 QO 00 W 00 00 W OD OJ - 00 OD W 00 00 ,..
O O O O O O O O�����-� --� --� -> ���� N N N N N N N N N N N N N N N N N N N N N N �p
�I �I �l V �I �l �l �I W W W W W �P A A A �P U� U7 Ut N N N W � � V �I �l �J �I �I �l 'J �l �l �I �I �I OD 00 N