HomeMy WebLinkAbout04/29/2014 Council Presentation - Utilities Sewer Line for Saguaro BloomTown of Marana
Saguaro Bloom
Tangerine/Downtown
Sewer Line Project
Map of Overall Project
Force Main
Force Main
Project Statistics
$2.0M design & construction cost
–
Town will pay, reimbursement through impact fee
–
program
Details
–
Length 9,100 feet
10-inch diameter
From existing lift station to existing 12-inch diameter gravity
sewer.
Utility easements from Pima County Flood Control, BKW Farms,
CMEX
Project Review
Benefits of Providing Sewer Service to Saguaro
Bloom
Provides a larger rate base to support the
wastewater utility
Obtain additional water resources
Relieves Rillito Vista satellite facility
Gravity Main
Gravity Main
(Property owners)
Crown West
Westcor
Gladden 2
Tangerine
I-10
Gravity Main
Project Statistics
$4M construction cost
–
Payment for design and construction will be
–
received from Development community through
development agreements
Details
–
8”, 12”, 15”, and 18” pipe diameters
19,400 feet long including side laterals & stubouts
Approximately 50 manholes
Connects to existing sewers from Clark Farms to Tangerine
Loop.
No property acquisition required
Timeline and Total Cost for
Project Phases
Phase I
(12 months)
Design Phase
–
Development Agreements
–
Return to council with Construction program
–
Phase II
(10 months)
Construction
–
Project Completion
–
Total Cost: $6M
Questions?