HomeMy WebLinkAboutSpecial Joint Study Session Agenda 01-11-2018MARANA TOWN COUNCIL
SPECIAL COUNCIL MEETING
NOTICE AND AGENDA
Ed Honea, Mayor
Jon Post, Vice Mayor
David Bowen, Council Member
Patti Comerford, Council Member
Herb Kai, Council Member
Carol McGorray, Council Member
Roxanne Ziegler, Council Member
Pursuant to A.R.S. § 38-431.02, notice is hereby given to the members of the Marana
Town Council and to the general public that the Marana Town Council and the Oro
Valley Town Council will hold a meeting open to the public on Thursday, January 11,
2018, at or after 11:30 AM, at the Hilton El Conquistador Resort, 10000 N. Oracle Road,
Tucson, Arizona.
This Notice and Agenda posted no later than Wednesday, January 10, 2018, 11:30 AM, at
the Marana Municipal Complex, 11555 W. Civic Center Drive, the Marana Operations
Center, 5100 W. Ina Road, and at www.maranaAZ.gov under Agendas and Minutes.
SPECIAL JOINT STUDY SESSION
CALL TO ORDER AND ROLL CALL
PLEDGE OF ALLEGIANCE
APPROVAL OF AGENDA
WELCOME / LUNCH
DISCUSSION
Marana Special Joint Study Session 01/11/2018 Page 1 of 2
DISCUSSION
Introductions1.
Presentation, update and discussion regarding the Tangerine Road/La Cholla Blvd.
projects
2.
Presentation, update and discussion regarding possible economic
development/tourism opportunities between the towns of Oro Valley and Marana
3.
Discussion of current and upcoming legislative issues4.
ADJOURNMENT
Marana Special Joint Study Session 01/11/2018 Page 2 of 2
Economic Development &
Tourism
Curt Woody, Economic Development &
Tourism Director, Town of Marana
Chris Cornelison, Assistant Town Manager,
Town of Oro Valley
Economic Development Activity
MARANA
•ED Strategic Plan – 2017
•Residential – Retail – Commercial
•Incentive Tools – MJCIP / DMRF
•Tourism
•Assets
•Gastronomy Tour
•Discover Marana
•Joint Initiatives
•Shared Asset – Tangerine Corridor
•Commercial – Retail – Residential
•State Land
Economic Development Activity
ORO VALLEY
•Town Strategic Plan – 2017
•Residential – Retail – Commercial
•Tourism
•Assets – Park Facilities, Roads, etc.
•Resort
•Major League Soccer
•National Synchronized Swimming
•Joint Initiatives
•Shared Asset – Tangerine Corridor
•Commercial – Retail – Residential
•State Land
Partnership Opportunities
•Tangerine Corridor
•How can we collaborate to enhance tourism and
economic development along this emerging
business/entertainment corridor?
•Recreation & Outdoors
•Move Across 2 Ranges
•Joint Trail Map
•What types of partnerships can we explore to offer
exciting recreational opportunities to residents and
visitors?
•Potential Synergies?
Tangerine Road/La Cholla Blvd.
Project Updates
Keith Brann, Town Engineer, Town of Marana
Paul Keesler, Town Engineer, Town of Oro Valley
RTA Partnership Projects
•Tangerine Road RTA Ballot project #1, periods 2,3,4
–DCR for entire corridor $3M
–Phase 1, Dove Mountain to La Cañada Drive
under construction $54M
–Phase 2, I-10 to Dove Mountain, $67M est.
•La Cholla Blvd RTA Ballot project #4, periods 2,4
–Phase 1, Magee to Overton including bridge
over CDO completed by Pima County $25M
–Phase 2, Overton to Tangerine, $23M est.
Tangerine Road Project Update
Keith Brann, Town Engineer, Town of Marana
Tangerine Road Project Overview
•5 Miles Through 3 Jurisdictions
•4-Lane Divided Roadway
•Landscaped Median
•100-year Wash Crossings
•Shared Use Path
•New Signal at Camino de Oeste
•Equestrian Signal Actuation
•Wildlife Linkage Accommodations
4-Lane Divided Roadway
Wildlife Enhancement
Tangerine Road Enhancements
•Marana paving of Thornydale
Road
•Marana additional path and
site grading for future park
•Marana public art feature
•Oro Valley and Marana
added conduit for fiber optic
•Oro Valley water line
replacement
•Pima County wastewater
force main and sleeve
Public Art
Tangerine Road Status
•Marana 4 Lane segment open
•Oro Valley segment 60% complete
–Traffic shifted to newer pavement
•Expected completion early fall 2018
Informational Website
www.tangerineroad.info
La Cholla Blvd. Project Update
Paul Keesler, Town Engineer, Town of Oro Valley
Phase 1 – Pima County Lead
•Completed in 2014
•1.7 miles
•$25 Million
•Bridge Over CDO Current
Project
Phase 2 – Oro Valley Lead
•3.5 miles
•Estimated $23 Million (RTA, OV, PC)
•Jurisdictions=80% OV, 20% PC
•Goals
•Increase Vehicle Capacity
•14,000 vpd (existing)
•24,000 vpd (2045)
•Improve Safety
•Increase Mobility
•All Weather Drainage Crossings
Sight Distance Issues
Lack of Shoulders, Dip Crossings, Limited Multi-
Modal Accommodations
Overton Road to Tangerine Road
Phase 2 - Overview
•Widen to four-lanes
•Curbed Median
•Turn Lanes
•Signals (Lambert, Naranja
and Glover)
•Landscape & Water harvesting
•Bicycle lanes, MUP, Sidewalks,
and ADA
•Tie into Tangerine Road Project
Project Schedule
•Design - Completed
•Right of Way Acquisitions – in progress
•Utility Relocations – in progress and design
•Roadway Construction -
•Summer 2018
•24 Months
Public Information
Sign up for updates and provide comments at:
www.lachollaimprovements.info
Tangerine Road Ribbon Cutting
Joint Ribbon Cutting Early Fall 2018