2017 Council Direction
FY18 CIP project ST059 – Adonis Road Extension
Project Status•Resolution 2018‐011 Authorized ROW Acquisition February 2018•5 Property owners•4 dedications•1 condemnation•Possession completed on October 8
Project Timeline•October 8, 2018 Letter sent to TMR Investors notifying of ROW clearance•October 17, 2018 Engineering scoping meeting held•March 7, 2019 TMR Investors must submit design (150 days)•180 days after approval TMR Investors must begin construction of Adonis Road Extension•1 year after completion TMR Investors must begin construction of Marana TI improvements•Uncertain Final order of condemnation
Open Discussion