HomeMy WebLinkAboutStudy Session Presentation 10-23-2018 Adonis Road ExtensionAdonis Road ExtensionKeith Brann, Town EngineerOctober 23, 2018 2017 Council Direction FY18 CIP project ST059 – Adonis Road Extension Project Status•Resolution 2018‐011 Authorized ROW Acquisition  February 2018•5 Property owners•4 dedications•1 condemnation•Possession completed on October 8 Project Timeline•October 8, 2018  Letter sent to TMR Investors notifying of ROW clearance•October 17, 2018   Engineering scoping meeting held•March 7, 2019 TMR Investors must submit design (150 days)•180 days after approval TMR Investors must begin construction of Adonis Road Extension•1 year after completion TMR Investors must begin construction of Marana TI improvements•Uncertain Final order of condemnation  Open Discussion