HomeMy WebLinkAboutCouncil Presentation 08/03/2022 - Water Infrastructure Improvement Plans 2023-2032Water and Water Reclamation Infrastructure Improvement Plans –2023-2032
Jing Luo, PhD, PE –Water Director
Erik Christenson, PE –Water Engineering Manager
August 2022
New LUA Predicted a Fast Growing Community
2
Water Customers
•Total Connections as of May 2022 = 10,285
•In 5 years -Increase by 50%
•In 10 years –Increase by 94%
Water Reclamation Customers
•Total Connections as of May 2022 = 5,926
•In 5 years –Increase by 72%
•In 10 years –Increase by 143%
3
New Water Infrastructure
Improvement Projects
4
Level of Service
•Water
•Source
•Wells
•Treatment
•Storage
•Reservoirs
•Transmission
•Booster Stations
•Pipelines
•Wastewater
•Treatment
•Conveyance
5
2022 Benefit Areas North Marana
IGA
Twin Peaks
Palo
Verde Saguaro
Bloom
Number of Development Units in the Next 10 Years
6
Saguaro Bloom Palo Verde IGA
North Marana Tangerine Business Park HV1 HV2 HV3 Picture Rock Airport Saguaro Bloom Palo Verde IGA
8597 224 1530 107 219 92 40 850 0 546
850 0 546
Twin Peaks
1988
North Marana
8821
7
2022 Benefit Area Growth
North Marana
IGA
Twin Peaks
Palo
Verde Saguaro
Bloom
1,988
5,4688,821
5,112
1,699
85060
0
546
NORTH MARANA PROJECTS
8
Marana Park
Reservoir and Well
Heritage Park
Water Plant
East Tangerine
16-inch Pipeline
9
Tangerine
Pipeline and
Break Tanks
C-Zone
Booster
Station
B-Zone Booster
Station and
Transmission Main
Sanders
Road
24-inch
Honea East
Plant Upgrades
NWRRDS Booster
Station NWRRDS
Pipeline
NWRRDS Forebay
and Marana
Independent
Booster
NORTH MARANA PROJECTS
Airport Booster
Station
Twin Peaks / Picture Rocks
10
Twin Peaks
Interconnect
Picture Rocks
Interconnect
Marana Park
11
•1.5 MG Reservoir
•$4,566,723 total
•$3,566,723 on Impact Fee
•1,000gpm Well
•$991,302
Heritage Park
12
•Two 900,000 Gallon
Reservoirs
•1,000gpm well
•1,250gpm Booster
•$5,328,123 estimated cost
The “Loop”
13
•B-zone Booster and Transmission Main
•$4,413,278
•B-Zone reservoir
•$617,700
•C-Zone Booster
•$1,819,375
•Tangerine 16-inch with Break Tanks
•$5,307,960
•Tangerine 16-inch at I-10
•$2,634,128
Northwest Recharge, Recovery and Delivery
System (NWRRDS)
•Partnered NWWRDS Project
•$8,506,697 Total
•$4,253,348.50 to Impact Fees
•Marana Booster at NWRRDS
•$4,799,440 Total
•$2,399,720 to Impact Fees
•Blending Plan
•$120,000
•$60,000 to Impact Fees
Airport Connection to NWRRDS
15
•New
•3,000gpm Airport Booster
•1,500gpm NWRRDS Booster
Station
•SE Well Upgrades
•$4,050,163 estimated cost
•$2,025,082 to Impact Fee
Other Pipelines Projects
16
•Sanders Road 24-inch
•$4,878,502
•Twin Peaks Interconnect
•$2,901,250
•Picture Rocks Interconnect
•$1,544,163
Water Infrastructure Impact Fee Projects –10 Year
17
50% Airport Connection to NWRRDS Pipeline (2PSs and 1 Well Rehab)4,050,163.00$ 2,025,081.50$
50% Partnered NWRRDS Project 8,506,697.00$ 4,253,348.50$
50% Marana Booster at NWRRDS 4,799,440.00$ 2,399,720.00$
50% Blending Plan 120,000.00$ 60,000.00$
B-Zone Booster and Transmission Line 4,413,278.00$ 4,413,278.00$
B-Zone Reservoir 617,700.00$ 617,700.00$
C-Zone Booster 1,819,375.00$ 1,819,375.00$
Tangerine 16" with Break Tanks 5,307,960.00$ 5,307,960.00$
Tangerine 16" at I-10 2,634,128.00$ 2,634,128.00$
Marana Park Well 991,302.00$ 991,302.00$
Marana Park Reservoir 4,566,723.00$ 3,566,723.00$
Sanders Road 24” Pipeline 4,878,502.00$ 4,878,502.00$
Twin Peaks Interconnect 2,901,250.00$ 2,901,250.00$
Picture Rocks Interconnect 1,554,163.00$ 1,554,163.00$
Honea East 216,550.00$ 216,550.00$
Heritage Park Water Plant 5,328,123.00$ 5,328,123.00$
Subtotal:52,705,354.00$ 42,967,204.00$
Projects Est. Impact Fee CostsEst. Project Costs
NWRRDS
The "Loop"
Categories
18
New Water Reclamation
Infrastructure Improvement
Projects
WRF Influent Flow Projection vs. Treatment Capacity
19
0.0
0.5
1.0
1.5
2.0
2.5
3.0
2016201720182019202020212022202320242025202620272028202920302031203220332034203520362022 Est Flows in MGD @140 2017 Est Flows in MGD @140
Flows in Million Gallons per Day (MGD)
Marana Water Reclamation
Facility (WRF) Phase 2
Expansion•Built in 2018 1.5 MGD
•Next Expansion scheduled to be
completed by 2027 –3.0 MGD
•Build-out is 4.5 MGD
•50% to Water Reclamation and 50% to Water Resources
Impact Fee
Wastewater Improvements
21
North Marana Sewer
Interceptor (3-7)
Mandarina Offsite Sewer
(1 -completed)
Moore-Clark
Farms Sewer
Upgrades (10)
Stingray
Drive Sewer
Upgrades (9)
WRF Expansion (8)
Gravity Pipe, Lift
Station and
Force Main (11)
Meritage Gravity
Sewer (2)
Wastewater ImprovementsCIP Cost
22
Notes:
•50% of projects#3-7 will be
applied to impact fee
calculation -$6,957,066
•50% of project #8 (WRF
expansion) will be applied to
wastewater impact fee calc.
-$19,580,556
•50% of the cost of recharge
basin expansion will be
added -$2,002,383.
•Debt services costs will also
be factored in for final
impact fee calculation.
23
New Water Resource
Infrastructure Improvement
Projects and Acquisition
Recharge Basin
Expansion
•Estimated cost: $4,004,766
•50% to Water Reclamation
•50% to Water Resource
Notes:
•Debt services costs will also be
factored in for final impact fee
calculation.
24
Renewable Water
Resource Acquisition
•Non-Indian Agriculture (NIA) CAP
Water
•515 acre-feet
•$1,072,743
•Other renewable sources
•$11,000-$12,000 per AFY
(with 100-year assurance)
•773 acre-feet
•$8,889,500
•Water Resources Master Plan
•$435,000
•50% of WRF expansion will be applied
to water resources impact fee calc. -
$19,580,55625
Project Costs Summary
26
Categories Estimated Project
Cost
Costs Applied to
Impact Fees
Percentage to
Impact Fees
Water Infrastructure Projects $52,705,354 $42,967,204 81.5%
Water Reclamation
Infrastructure Projects $48,842,121 $41,885,055 85.8%
Water Resources Projects $31,980,182 $31,980,182 100%
Questions/Discussion
27
Thank You !
Summary of Timeline
28
5/13/2022 Publication of draft LUA and IIP’s
6/23/2022 Stakeholder Outreach Meeting
8/3/2022 Public Hearing for LUA and IIP’s
9/6/2022 Council Action on LUA and IIP’s
9/9/2022 Notice of Intent to Implement Impact Fees
10/18/2022 Public Hearing for Impact Fees
12/6/2022 Council Action for Impact Fees
2/20/2023 Impact Fees Effective (min 75 days from council action)