HomeMy WebLinkAboutCouncil Presentation 11/01/2022 - Marana Utility Impact Fees WaterPublic HearingWater and Water Reclamation Impact Fees
Jing Luo, PhD, PE –Water Director
November 1, 2022
Agenda
1.Water Impact Fee Process Overview
2.Water Infrastructure Impact Fees
3.Water Reclamation Impact Fees
4.Water Resources Impact Fees
5.Summary of Proposed Fees
2
3
Impact Fee Process
Overview
Impact Fee Process
1.Recovers infrastructure and resources costs to serve new
customers from 2023 -2032
2.Growth and Cost projections per Town Land Use Assumptions
(LUA) and Infrastructure Improvement Plans (IIP)
3.Growth related costs only at existing service levels
4.Fee types: Water Infrastructure, Water Resources, Water
Reclamation
5.Fee is a unit cost calculation -Growth related costs ($) /
equivalent dwelling units (EDUs)
4
Impact Fee Calculation Methods
1.Incremental Method
a.New development supported by new infrastructure only
b.Projected costs / projected EDUs
c.Used for Water Infrastructure Fee
2.Hybrid Method
a.New development supported by both existing and new infrastructure
b.(Costs for existing + new infrastructure)/ total benefiting EDUs (existing and future)
c.Acknowledges costs already incurred to serve new development and recovers new
development’s proportionate share
d.Used for Water Resources and Water Reclamation Fees
5
6
Water Infrastructure Impact
Fees
Water Infrastructure Impact Fees Calc.
1.Incremental Method –New projects / new EDUs
2.Benefit Areas: North Marana, Twin Peaks, Saguaro Bloom, Palo Verde, and IGA
3.EDUs added –North Marana (8,821), Twin Peaks (1,988), Saguaro Bloom (850), and IGA (546) -Total (12,205)
4.New Infrastructure Projects Identified in North Marana and Twin Peaks Only
5.Infrastructure Costs
a.Projects which benefit two areas -Allocated proportionate to EDUs
b.Projects which are specific to a benefit area –Directly allocated
6.Other Eligible Costs –Water Master Plan, Impact Fee Study, Hartman Vistas Debt
7.Credit provided for existing fund balance
8.Fee calculated per EDU, scaled by AWWA meter capacity ratios
7
Water Infrastructure Benefit Areas
8
Water Infrastructure Impact Fee Unit Cost9
Description System-Wide North Marana Twin Peaks
Impact Fee Costs
50% Airport Connection to NRWWDS Pipeline $ 2,025,081 $ 1,652,627 [1]$ 372,455 [1]
50% Partnered NRWWDS Project 3,735,894 3,048,785 [1]687,109 [1]
50% Marana Booster at NRWWDS 2,107,775 1,720,111 [1]387,664 [1]
50% Blending Plan 60,000 48,965 [1]11,035 [1]
B-Zone Booster and Transmission Line 4,413,278 3,601,584 [1]811,694 [1]
B-Zone Reservoir 617,700 504,092 [1]113,608 [1]
C-Zone Booster 1,819,375 -1,819,375
Tangerine 16" with Break Tanks 5,307,960 5,307,960 -
Tangerine 16" at I-10 2,634,128 2,634,128 -
Marana Park Well 991,302 991,302 -
78% Marana Park Reservoir 3,566,723 3,566,723 -
Sanders Road 24” Pipeline 4,878,502 4,878,502 -
Twin Peaks Interconnect 2,901,250 -2,901,250
Picture Rocks Interconnect 1,554,163 -1,554,163
Honea East Well 216,550 216,550 -
Heritage Park Water Plant 5,328,123 5,328,123 -
Master Plan 150,000 122,412 [1]27,588 [1]
Impact Fee Study 60,000 48,965 [1]11,035 [1]
Hartman Debt Service Reimbursements 1,573,010 -1,573,010
Total Impact Fee Costs $ 43,940,814 $ 33,670,829 $ 10,269,985
Divided by: New EDUs 10,809 8,821 1,988
Equals: Infrastructure Cost per EDU $ 3,817 $ 5,166
Less: Balance on 8/23/2022 $ 4,993,825 $ 4,075,357 [1]$ 918,468 [1]
Divided by: New EDUs 10,809 8,821 1,988
Equals: Credit for Balance per EDU $ 462 $ 462
Water Infrastructure Fee per EDU (Infrastructure Cost -Balance)$ 3,356 $ 4,704
Source(s): Impact Fee Costs (Table 4), Balance on 8/23/2022 (per Town), EDUs (Table 3)
[1] Split proportionate to EDUs
10
Water Reclamation
Impact Fees
Water Reclamation Impact Fee Calc.
1.Hybrid Method –Water Reclamation Facilities (WRF) + Recharge
2.Single benefit area for Town Designated Management Area (DMA)
3.Benefiting EDUs -Water Reclamation Facility (WRF) and Recharge Basin
a.Current 1.5mgd capacity will have capacity until 2027
b.New 1.5mgd expansion will provide capacity beyond 2032
c.Total capacity recognizes all customers who will use WRF
d.3mgd / 139.6gpd per EDU = 21,490 EDUs
4.Incremental Method –Collection System (New 9,267 EDUs)
5.Other Eligible Costs –Sewer Master Plan, Impact Fee Study
6.Credit provided for existing fund balance
7.Fee calculated per EDU, scaled by AWWA meter capacity ratios
11
Town Sewer Service Area (DMA)
12
Water Reclamation Unit Cost13
Description System-Wide % Impact Fee
Funded Water Rec Share
WRF Costs
WRF 2013 Principal and Interest $ 34,527,164 50%$ 17,263,582
WRF 2017A Principal and Interest 32,096,067 50%16,048,033
WRF 2017C Principal and Interest 4,702,544 50%2,351,272
WRF Loaned from Transportation Fund 2,400,000 50%1,200,000
WRF Loaned from Water Fund 367,388 50%183,694
WRF Loaned from Wastewater Fund 3,169,279 50%1,584,640
WRF Expansion Principal and Interest 62,847,780 50%31,423,890
Recharge Expansion Principal and Interest 6,427,056 50%3,213,528
Subtotal: Water Reclamation Facility (WRF)$ 146,537,278 $ 73,268,639
Divided by: Total EDUs 21,490
Equals: WRF Cost per EDU $ 3,409
Subtotal: Collection System $ 27,584,477 75%$ 20,627,411
Divided by: New EDUs 9,267
Equals: Collection System Cost per EDU $ 2,226
Sewer Master Plan $ 150,000 100%$ 150,000
Impact Fee Study $ 60,000 100%$ 60,000
Divided by: New EDUs 9,267
Equals: Impact Fee Study and Master Plan Cost per EDU $ 23
Less: Balance on 8/23/2022 $ 6,144,392 100%$ 6,144,392
Divided by: New EDUs 9,267
Equals: Credit for Balance per EDU $ 663
Water Reclamation Fee per EDU (WRF + Collection + IF Study -
Balance)$ 4,995
Source(s): Impact Fee Costs (Table 14), Balance on 8/23/2022 (per Town), EDUs (Table 13)
14
Water Resources Impact
Fees
Water Resources Impact Fees Calc.
1.Hybrid Method –for Water Resources from Effluence and Other Sources
2.Single benefit area -entire water service area
3.Benefiting EDUs
a.WRF Effluent –3mgd / 270gpd per EDU = 11,111 EDUs
b.Additional Resources Acquisitions –
i.NIA/CAP –242 AFY (216,044 gpd) / 270 gpd per EDU = 800 EDUs
ii.Additional Acquisitions –773 AFY (690,090 gpd) / 270 gpd per EDU = 2,556 EDUs
c.Total 14,467 EDUs
4.Other Eligible Costs –Integrated Water Resources Master Plan, Impact Fee Study
5.Credit provided for existing fund balance
6.Fee calculated per EDU, scaled by AWWA meter capacity ratios
15
Water Resources Unit Cost16
Description System-Wide % of Impact Fee
Funded Water Resources
Impact Fee Costs
WRF 2013 Principal and Interest $ 34,527,164 50%$ 17,263,582
WRF 2017A Principal and Interest 32,096,067 50%16,048,033
WRF 2017C Principal and Interest 4,702,544 50%2,351,272
WRF Loaned from Transportation Fund 2,400,000 50%1,200,000
WRF Loaned from Water Fund 367,388 50%183,694
WRF Loaned from Wastewater Fund 3,169,279 50%1,584,640
WRF Expansion Principal and Interest 62,847,780 50%31,423,890
Recharge Expansion Principal and Interest 6,427,056 50%3,213,528
NIA/CAP 1,072,743 50%1,072,743
Additional Water Resources 8,889,500 50%8,889,500
Integrated Water Resources Plan 435,000 50%435,000
Impact Fee Study Expenses 60,000 50%60,000
Total Impact Fee Costs $ 156,994,521 $ 83,725,882
Divided by: Total EDUs 14,467
Equals: Resources Cost per EDU $ 5,787
Less: Balance on 8/23/2022 $ 5,248,244 100%$ 5,248,244
Divided by: New EDUs 12,205
Equals: Credit for Balance per EDU $ 430
Water Resources Fee per EDU (Resources Cost -Balance)$ 5,357
Source(s): Impact Fee Costs (Table 9), Balance on 8/23/2022 (per Town), EDUs (Table 8)
17
Proposed Water Impact Fees
Summary
Summary of Water, Water Resources and Water Reclamation Impact Fees
18
Description
Water Infrastructure Water
Resources
Water
ReclamationNorth Marana Twin Peaks Saguaro
Bloom
Existing
5/8"$ 2,331 $ 2,740 $ 838 $ 3,050 $ 3,930
3/4"3,497 4,110 1,257 4,575 5,895
1"5,828 6,850 2,095 7,626 9,824
1 1/2"11,656 13,700 4,189 15,251 19,648
2"18,650 21,920 6,703 24,402 31,437
Calculated Fee
5/8"$ 3,356 $ 4,704 $ 838 $ 5,357 $ 4,995
3/4"5,033 7,056 1,257 8,036 7,493
1"8,388 11,760 2,095 13,394 12,488
1 1/2"16,776 23,520 4,189 26,787 24,975
2"26,841 37,632 6,703 42,859 39,960
Primary Drivers of Water Related Fees
1.Rapid growth from a small community to a mid-sized community
requires infrastructure
2.Town Council’s direction: developments should pay for the cost of
growth
3.Inflation –project construction costs drastically increased
4.Regional water supplies –water resources cost increased
5.Town has decided to contribute:
a.~$8MM general fund to the NWRRDS projects
b.~$3MM general fund to the phase I of WRF
c.~$7MM for sewer collection augmentation projects
6.WIFA contributed ~$500K forgivable principal for Marana Parks
Reservoir Project 19
Marana Home Value Marana Home Value:
•2017 –$255K
•2022 -$441K
•Increased by: $186K (73%)
Water Related Impact Fees:
•Existing (2017):
$9,772 –$12,150
•4.3%of the home value
•Proposed (2022):
$13,988 -$18,820
•3.7%of the home value
20
Questions/Discussion
21
Thank You !