HomeMy WebLinkAboutCouncil Presentation 11/15/2022 - Santa Cruz River Management PlanSanta Cruz River
Management Plan
Proposed Projects in the Town of
Marana
Evan Canfield –Pima County Regional Flood
Control District
Kevin Payne –Kimley Horn.
Santa Cruz River Mgt Plan –Grant Rd to Pinal Co
•Project Purpose
The purpose of the Santa Cruz River
Management Plan is to develop a
management strategy to balance flood
risk management, drainage infrastructure
protection, water recharge, recreation
opportunities, public safety and riparian
habitat preservation for the Santa Cruz
River from Grant Rd to Pinal County.
2
http://www.pima.gov/santacruzriverplan/
Three ‘a Living River’ Reporting
Reaches (2013 to present) are the basis
for Three Management Plan Reaches
Three Rivers/Corazon (Agua
Nueva to Tres Rios)
Cortaro Narrows (Tres Rios
to Avra Valley Rd)
Marana Flats (Avra Valley Rd
to Trico Rd)
How We Got Here
Santa Cruz River Management Plan
Phase 1
Results
Alternatives
Identification
and Selection
Concept
Plans Implementation Plan
Stakeholder Input
CONCEPT
ADVANCEMENT
Stakeholder Preferences By Reach
USACE Multi-Criteria Decision Analysis (MCDA) protocol
5
32.6
21.6
36.7
14.1
16.5
11.7
22.8
24.2 12.6
9.6
12.1 8.6
11.7
7.7 17.3
9.1 18 13.2
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Grant to Ina Ina to Avra Avra to Pinal
Flood Control Water Resources
Environment Recreation
Community Compatibility Public Safety
19.9 20.9 25.1
10.4 6.2
8.2
13.5
11
8.3
8 12.7 8.9
14.4 17 8.3
7.7 7.6
4
10.3 9.1
8.8
5.7 5.3
4
4.9 4.8
13.5
5.2 5.5 8.8
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Grant to Ina Ina to Avra Avra to Pinal
Floodplain Management Transportation
Water Security Emergency Response
Natural and Cultural Public Use
Sustainability Unauthorized Uses
Economic Vitality Feasibility/Implementation
Project Type Alternatives Weighting Criteria
Alternatives Selection Report
6
7
Santa Cruz River Mgt Plan –Project 4
8
Santa Cruz River Mgt Plan –Project 5
9
Santa Cruz River Mgt Plan –Project 6
10
Wildlife Ramp on East Bank near El Rio PreserveProject 7
11
Effluent Training Features along the LSCR Levee
Project 8
Santa Cruz River Management Plan: Alternative 8
12
New Wetland near CAP Crossing –Project 9
13
Accessibility Improvements to River –Project 10
14
Wall for Freeboard and Trailhead Enhancements -11
15
Sanders Road Bridge Replacement over Santa
Cruz River -Project 12
Santa Cruz River Management Plan: Alternative 12
16
Trico-Marana Rd Bridge Replacement -Project 15
Santa Cruz River Management Plan: Alternative 15
17
Trico Rd Bridge Replacement -Project 16
Santa Cruz River Management Plan: Alternative 16
18
LSCR Levee Extension, Sanders Rd to Trico Rd
Project 13
Santa Cruz River Management Plan: Alternative 13
19
Multi-Use Multi-Objective Channel
20
All
Non-Structural Project -Vegetation Management Plan
Non-Structural Project -Update FEMA Floodplain Maps Downstream of Sanders Rd
(Approved by FEMA, awaiting map Publication)
How We Got Here
Santa Cruz River Management Plan
Phase 1
Results
Alternatives
Identification
and Selection
Concept
Plans Implementation Plan
Stakeholder Input
CONCEPT
ADVANCEMENT
Implementation Plan
23
Santa Cruz River Mgt Plan –Grant Rd to Pinal County
•How did we get here?
•15% design-level costs
•Contingency added
(20% -30%)
24
Santa Cruz River Mgt Plan –Grant Rd to Pinal County
•How did we get here?
•Implementation Schedule was developed
25
Summary Report
26
INCLUDES:
•EXECUTIVE SUMMARY
•SUMMARY OF ALL DELIVERABLES &
RECOMMENDATIONS
•RECOGNITION OF ALL CONTRIBUTORS
•Appendix A –Public Participation Report
•Appendix B –Stakeholder Engagement
Summary
Santa Cruz River Mgt Plan –Grant Rd to Pinal County
•Process Remaining
•Endorsed by Jurisdiction Decision Makers
•Flood Control District Advisory Committee
•Pima County Board of Supervisors
•Town of Marana
•City of Tucson
27
http://www.pima.gov/santacruzriverplan/
Evan Canfield
Pima County Regional Flood Control District
evan.canfield@pima.gov
Kevin Payne
Kimley-Horn
Kevin.Payne@kimley-horn.com